Skip to content
CEGR 493
Design
Week 4
water
Hydraulic Design Office
Capstone II dashboard

Watershed Delineation

Delineate the contributing drainage area and its physical characteristics.

Section progress

0% of the workflow complete

Water Resources · Watershed hydrology, stormwater, channels, culverts, networks and hydraulic structures.

Deliverable: Watershed delineation map with basin parameters (area, CN, Tc) tabulated.

Minimum tables, figures and equations for Watershed Delineation

Tables — at least 7

  • Table — trial sections or sizes considered, with the capacity of each and the selection decision
  • Table — final selected geometry for every element: dimensions, thickness, grade, spacing, elevation
  • Table — inlet, pipe, culvert and outlet sizing with slope, capacity and headwater depth
  • Table — ultimate limit state check summary: demand, capacity, ratio, pass or fail, governing clause
  • Table — serviceability check summary: deflection, crack width, settlement, freeboard or velocity against its limit
  • Table — factors of safety achieved against the factor required, per failure mode
  • Table — pre- versus post-development peak flows by design storm

Figures — at least 5

  • Figure — free body diagram of each isolated element, fully labelled with loads, reactions, dimensions and axes
  • Figure — shear and moment (or pressure and velocity) diagrams for each force-carrying element
  • Figure — dimensioned section or plan of each designed element
  • Figure — capacity versus demand plot, interaction diagram, or rating curve as applicable
  • Figure — hydraulic grade line and energy grade line profile

Equations — at least 8

  • Equation — equilibrium equations written out for each free body (sum of forces and sum of moments, or continuity and energy)
  • Equation — the internal force relations V(x) and M(x), or the momentum/thrust relation, used to compute each element's demand
  • Equation — the resulting demand at the critical section of each element, with numeric substitution
  • Equation — the capacity expression for each element type, shown with full numeric substitution and units
  • Equation — the sizing criterion that sets the final dimension (for example required area, depth or diameter)
  • Equation — each limit state check written as demand over capacity with numbers substituted
  • Equation — the factor of safety calculation for each failure mode checked
  • Equation — outlet scour velocity and riprap sizing check

Number every table and figure (Table 4.x, Figure 4.x), caption it, and refer to it by number in your text. Number displayed equations and show the substitution with units. These counts are minimums — add whatever else your design needs.

Engineering documentation standard — required in every Chapter 4 subsection

These rules are graded on every subsection. Work that misses them is capped on technical accuracy, exhibits, codes and communication, whatever the quality of the prose.

Code and standard references

  • Every requirement, factor, coefficient, limit and allowable you apply cites the governing document AND the exact section, article or sub-article number — e.g. ACI 318-19 §22.5.5.1, AISC 360-22 Chapter J, Section J3.6, AASHTO LRFD 10th Ed. Article 3.6.1.2.2, ASCE 7-22 §12.8.1, ASTM D2487, state DOT manual section, local stormwater manual chapter.
  • Give the edition or year of every document the first time it appears, then use a consistent short form.
  • Where a code equation is used, quote the equation number (e.g. Eq. 22.5.5.1) next to your displayed equation.
  • Where you depart from a code provision, state the clause you are departing from and the engineering justification.
  • List every code, standard and manual actually used in a Codes and Standards table at the start of the subsection.

Citations for statements

  • Every statement of fact, value taken from elsewhere, material property, soil parameter, rainfall depth, unit cost or published method carries an in-text citation (APA) to its source.
  • Field and lab data cite the report, boring log, gauge, survey file or test number and its date.
  • Manufacturer data cites the product literature and revision date; software results cite the program, version and model file name.
  • Uncited assertions are treated as assumptions and must appear in the assumptions table with a justification.
  • Every in-text citation resolves to a full entry in the reference list.

Step-by-step calculations

  • Structure every calculation the same way: (1) objective, (2) governing code clause, (3) equation in symbolic form with the equation number, (4) definition of each symbol, (5) numerical substitution, (6) result with units, (7) comparison against the limit and the pass/fail statement.
  • Show the substitution line — never jump from the formula to the answer.
  • Number displayed equations sequentially (Eq. 4.1, 4.2, …) and refer to them by number in the text.
  • State the load or flow combination governing each calculation by name.
  • Carry consistent significant figures and round only at the reported result; state the rounding convention once.
  • Present repetitive element checks in a calculation table with one row per element and the same column order throughout.

Free body diagrams and figures

  • Draw a separate free body diagram for each isolated element — no combined sketches standing in for several members.
  • Dimension every FBD: span, depth, thickness, cover, eccentricity, embedment, slope, pipe diameter, wall height — with the dimension lines and values shown.
  • Label every force, pressure, reaction and moment with its symbol, magnitude and units, and show the sign convention and coordinate axes.
  • Show supports and boundary conditions explicitly (pin, roller, fixed, elastic, buoyant, hydrostatic).
  • Accompany each FBD with its shear, moment, thrust, pressure or hydraulic grade diagram at the same scale reference.
  • Number and caption every figure (Figure 4.x) and refer to it by number in the narrative; add a scale or north arrow to plans.

Units and notation

  • Every number in text, tables, figures and equations carries its unit — no bare numbers.
  • Use one unit system throughout (US customary or SI); if both appear, give the converted value in parentheses consistently.
  • Check dimensional homogeneity of each equation and say so — the units of both sides must match.
  • Provide a nomenclature table defining every symbol with its unit.

Checking and verification

  • Every calculation is checked by an independent route — hand check against software, alternative method, order-of-magnitude estimate, or a published worked example — and the check is shown, not just claimed.
  • Report demand-to-capacity ratios and factors of safety against the required values, with the source clause for each required value.
  • Include a verification/checking table: item, method of check, expected, obtained, difference, accept or revise.
  • Sanity-check every result (magnitude, direction, plausibility) and state the conclusion.
  • Record who checked the work and on what date; flag anything still unverified as an open item.
  • State limitations and the range over which the result is valid.

How to complete this section

0 words saved

Do this next: Read the Watershed Delineation lecture and the worked example so you know what "Watershed delineation map with basin parameters (area, CN, Tc) tabulated." has to contain.

Not sure how to start or how much depth is expected? Read the fully written model example for this deliverable first — it shows the structure, tables and level of justification your advisor grades against.

Hydraulic Design Office — what this workspace teaches

Watershed hydrology, stormwater, channels, culverts, networks and hydraulic structures.

  • Watershed delineation, land use, curve number and imperviousness
  • Rainfall: IDF curves, design storms, return periods
  • Rational Method and NRCS/SCS runoff methods with validity limits
  • Hydrograph development and flood routing (HEC-HMS concepts)
  • Open channel flow: Manning's equation, normal and critical depth, froude number
  • Culvert hydraulics: inlet vs. outlet control, headwater, performance curves
  • Storm sewer network design and hydraulic grade line
  • Detention basin sizing, stage-storage-discharge and outlet structures
  • Weirs, orifices and energy dissipation structures
  • Stormwater BMPs, water quality volume and EPA guidance

End-of-term milestones

  • Tuesday, November 17, 2026 — Poster printed and ready. 36 in × 48 in poster finalized and printed one week before the November 24 showcase.
  • Wednesday, November 18, 2026 — Final document package uploaded for scoring. Chapters 4–5, calculation package, drawings and appendices uploaded in the app for advisor scoring.
  • Wednesday, November 18, 2026 — Poster presentation to faculty and industry. Wednesday poster session — printed 36 in × 48 in poster presented in person; industry reviewers score communication and impact.
  • Wednesday, November 25, 2026 — Oral presentation and defense (scored). Scored oral presentation and defense held on Wednesday, November 25.
Week 4
water
Water Resources

Watershed Delineation

Delineate the contributing drainage area and its physical characteristics.

Section B

Engineering story

A real project situation that frames this module

Week 4: watershed delineation is the item standing between the team and a reviewable hydrologic and hydraulic model with the sized conveyance. Delineate the contributing drainage area and its physical characteristics. Review stalls on a single line: the team cannot show the record behind watershed/subbasin delineation from topographic (LiDAR-derived) data.

Using a sheet flow length longer than the 100 ft TR-55 limit without switching to shallow concentrated flow. Because time of concentration (Tc) computation via segmented flow paths (sheet, shallow concentrated, channel), the error does not stay local: it is carried into the design of record that drawings, quantities and cost are generated from, and every downstream product inherits it before anyone notices.

Downstream property owners, emergency responders and the utility carry the consequence. On this module specifically, the exposure runs through curve number (CN) assignment from NRCS soil and land cover data, and the cost of correction rises every week the hydrologic and hydraulic model with the sized conveyance moves closer to issue.

Decisions the engineer must make

  • What record establishes watershed/subbasin delineation from topographic (LiDAR-derived) data, and is that record in the project data inventory?
  • Does NRCS TR-55 (Current), Ch. 3, govern here — and is that the edition adopted by the jurisdiction?
  • What is the acceptance criterion for time of concentration (Tc) computation via segmented flow paths (sheet, shallow concentrated, channel), and was it written before the result was known?
  • Is Tc = (0.007·(n·L)^0.8)/(P2^0.5·S^0.4) valid over the parameter range this project actually occupies?
  • If the check fails, does the team revise the hydrologic and hydraulic model with the sized conveyance or raise a change request against the locked baseline?
Row of centrifugal pumps and valved steel piping inside a water pumping station.

Photo 1. Pump station: where system head curve, pump curve and operating point meet real hardware.

Capstone Studio instructional photograph

Section C

Why this matters

Professional

A licensed engineer defending watershed delineation cites NRCS TR-55 (Current), Ch. 3, and shows the record behind each input. Your watershed delineation map with basin parameters (area, cn, tc) tabulated. is reviewed the same way — traceability is assessed before arithmetic.

Technical

Watershed/subbasin delineation from topographic (LiDAR-derived) data is what makes Tc = (0.007·(n·L)^0.8)/(P2^0.5·S^0.4) usable on this project rather than a formula copied from a reference. Get it wrong and every quantity derived from it is wrong by the same factor.

Safety

The failure mode this module guards against is a conveyance or storage element overtopped by the design event. It reaches people through basin characteristics, which is why the safety check is recorded explicitly here rather than inferred from a passing strength or performance check.

Economic

The design of record that drawings, quantities and cost are generated from is priced from this work. Quantities, unit costs and schedule float all trace to watershed/subbasin delineation from topographic (LiDAR-derived) data; a late correction here is paid for as a change order, not a redline.

Environmental

Environmentally, this module fixes receiving-water quality, channel erosion and altered baseflow. Choosing conservatively without justification is not free — the excess shows up as material, energy and land that the project consumes for no measurable gain.

Community

Watershed delineation and curve numbers must be updated to reflect current land use, not the land use at original design. Households and businesses in the floodplain the design is meant to protect live with that outcome long after the semester ends.

Section D

Learning objectives

By the end of this module you will be able to:

  1. 1.Compare watershed/subbasin delineation from topographic (LiDAR-derived) data, using this project's own conditions rather than a textbook case.
  2. 2.Analyze time of concentration (Tc) computation via segmented flow paths (sheet, shallow concentrated, channel), using this project's own conditions rather than a textbook case.
  3. 3.Justify curve number (CN) assignment from NRCS soil and land cover data, using this project's own conditions rather than a textbook case.
  4. 4.Explain basin characteristics, using this project's own conditions rather than a textbook case.
  5. 5.Compute the governing quantity from Tc = (0.007·(n·L)^0.8)/(P2^0.5·S^0.4), with a unit audit on every term.
  6. 6.Apply NRCS TR-55 (Current), Ch. 3, and cite the section that governs your acceptance decision.
  7. 7.Reproduce the worked example for sheet flow segment and defend the interpretation of the result.
  8. 8.Produce watershed delineation map with basin parameters (area, cn, tc) tabulated. at a standard the floodplain administrator would accept without a second revision cycle.

Section E

Instructional content

Full lecture notes with figures and governing equations

Reading watershed delineation as a practising engineer

Delineate the contributing drainage area and its physical characteristics. That single sentence hides the substance of the module: watershed/subbasin delineation from topographic (LiDAR-derived) data, and time of concentration (Tc) computation via segmented flow paths (sheet, shallow concentrated, channel). Both must be established from project evidence before anything downstream is credible.

In water resources engineering, this work is the input to the hydrologic and hydraulic model with the sized conveyance. Curve number (CN) assignment from NRCS soil and land cover data — which is why this page asks you to record the source of every quantity, not just its value. The design of record that drawings, quantities and cost are generated from depends on it.

  • Watershed/subbasin delineation from topographic (LiDAR-derived) data
  • Time of concentration (Tc) computation via segmented flow paths (sheet, shallow concentrated, channel)
  • Curve number (CN) assignment from NRCS soil and land cover data
  • Basin characteristics: area, slope, length, imperviousness
FIGURE 1outlet / POIdivide1Basin divide2Flow path3Sheet flow4Shallow concentrated flow5Channel flow6Outlet point7CN8Tc
Figure 1. Watershed Delineation — annotated engineering schematic showing the governing quantities carried through this module.Read this figure alongside the theory block: every labelled quantity must appear in your calculation package with a unit and a source.
Water ponding in a street gutter and flowing into a curb storm drain inlet during rain.

Photo 1. Reading watershed delineation as a practising engineer in practice — Inlet capture during rainfall: gutter spread and inlet capacity decide whether the lane floods.

Capstone Studio instructional photograph

Governing relationships and how they are applied here

The relationships below govern watershed delineation. Tc = (0.007·(n·L)^0.8)/(P2^0.5·S^0.4) — each is valid only inside the parameter range this project occupies, so state that range before substituting.

Time of concentration (Tc) computation via segmented flow paths (sheet, shallow concentrated, channel) sets the values you place into these expressions. Any code-prescribed factor must match NRCS TR-55 (Current); a factor lifted from a different edition silently changes the answer.

Tc = (0.007·(n·L)^0.8)/(P2^0.5·S^0.4)

  • Tc = sheet flow travel time (h)
  • n = Manning roughness coefficient
  • L = flow length (ft, ≤100 ft)
  • P2 = 2-yr, 24-hr rainfall depth (in)
  • S = slope (ft/ft)
Three engineers in hard hats and safety vests reviewing drawings on a truck tailgate.

Photo 2. Governing relationships and how they are applied here in practice — Field review: the conversation in which a scope, a constraint or a decision is actually settled.

Capstone Studio instructional photograph

Constraints, adopted standards and the safety case for watershed delineation

NRCS TR-55 (Current), Ch. 3, governs this module: Time of concentration and travel time

The safety case is explicit here. The failure mode is a conveyance or storage element overtopped by the design event; the people exposed are downstream property owners, emergency responders and the utility; the control that prevents it is basin characteristics together with an independent check by someone who did not perform the work.

  • Controlling criterion for this module: watershed/subbasin delineation from topographic (LiDAR-derived) data.
  • Adopted reference: NRCS TR-55 (Current) — cite Ch. 3 by number.
  • Failure mode guarded: a conveyance or storage element overtopped by the design event.
  • Evidence produced: Watershed delineation map with basin parameters (area, CN, Tc) tabulated..
FIGURE 2Confirm inputs and sourcesSelect governing standardAnalyze / designCheck units and equilibriumIndependent checkAccept or revise
Figure 2. Watershed Delineation — professional workflow from inputs through acceptance.The revise loop is normal. Reviewers expect to see it in your version history.
Three engineers in hard hats and safety vests reviewing drawings on a truck tailgate.

Photo 3. Constraints, adopted standards and the safety case for watershed delineation in practice — Field review: the conversation in which a scope, a constraint or a decision is actually settled.

Capstone Studio instructional photograph

Where this method stops being valid

The worked example — sheet flow segment — holds only while its assumptions hold. This segment travel time is added to shallow concentrated and channel segment times to obtain total time of concentration. Outside that envelope the arithmetic still returns a number, and the number is wrong in a way no unit check will catch.

For this project, the boundary you are most likely to push is basin characteristics. If you cross it, say so in writing, bound the error, and carry the limitation into your results chapter. A disclosed limitation is professional practice; a silent extrapolation is not.

Three engineers in hard hats and safety vests reviewing drawings on a truck tailgate.

Photo 4. Where this method stops being valid in practice — Field review: the conversation in which a scope, a constraint or a decision is actually settled.

Capstone Studio instructional photograph

Section F

Engineering workflow

Steps

  1. 1. Assemble the inputs this module needs — watershed/subbasin delineation from topographic (LiDAR-derived) data; time of concentration (Tc) computation via segmented flow paths (sheet,… — each with a unit and a source record.
  2. 2. Confirm NRCS TR-55 (Current) is the adopted edition and locate Ch. 3.
  3. 3. State the assumptions and the acceptance criterion for watershed/subbasin delineation from topographic (LiDAR-derived) data.
  4. 4. Evaluate Tc = (0.007·(n·L)^0.8)/(P2^0.5·S^0.4) term by term, carrying one extra significant figure.
  5. 5. Test the result against curve number (CN) assignment from NRCS soil and land cover data.
  6. 6. Audit units and run an order-of-magnitude check by hand before the number leaves your desk.
  7. 7. Obtain an independent check from a teammate who did not perform the work, and record their name and date.
  8. 8. Assemble watershed delineation map with basin parameters (area, cn, tc) tabulated. and submit it to the floodplain administrator for review.

Decision points

  • Is every input behind watershed/subbasin delineation from topographic (LiDAR-derived) data traceable? If not — stop and collect the record.
  • Does the result satisfy time of concentration (Tc) computation via segmented flow paths (sheet, shallow concentrated, channel)? If not — revise the work, never the criterion.
  • Would the correction change the design of record that drawings, quantities and cost are generated from? If yes — raise a change-control request before proceeding.
  • Have you ruled out the most common error on this module — using a sheet flow length longer than the 100 ft TR-55 limit without switching to shallow concentrated flow?

Quality checklist

  • Documented: watershed/subbasin delineation from topographic (LiDAR-derived) data
  • Documented: time of concentration (Tc) computation via segmented flow paths (sheet, shallow concentrated,…
  • Documented: curve number (CN) assignment from NRCS soil and land cover data
  • NRCS TR-55 Ch. 3 cited by section number
  • Units audited on every expression
  • Acceptance criterion recorded before the result
  • Independent check signed and dated
  • Watershed delineation map with basin parameters (area, CN, Tc) tabulated. attached and named per the course convention

Section H

Interactive visualization

Watershed Delineation — step-through

Advance one frame at a time. Each frame adds one engineering decision to the previous state.

Rainfall–runoff

Step 1 of 6

Delineate basin boundary from topography

Section I

Applicable codes and standards

NRCS TR-55

Current · Ch. 3

Adopted design/analysis reference governing this module.

Relevance: Time of concentration and travel time

Reference the section number and edition in your calculation package. Do not reproduce code text.

Section J

Worked examples

Full engineering solution format

Section K

Common mistakes and how to avoid them

  • Using a sheet flow length longer than the 100 ft TR-55 limit without switching to shallow concentrated flow
  • Assigning a single CN to a mixed land-use basin without area-weighting
  • Delineating a basin from coarse contours instead of available LiDAR data
  • Treating watershed/subbasin delineation from topographic (LiDAR-derived) data as a given instead of establishing it from a project record.
  • Producing watershed delineation map with basin parameters (area, cn, tc) tabulated. without showing how time of concentration (Tc) computation via segmented flow paths (sheet, shallow concentrated,… was satisfied.
  • Substituting into Tc = (0.007·(n·L)^0.8)/(P2^0.5·S^0.4) outside the range where it is valid, and reporting the number anyway.
  • Missing basin characteristics, which is exactly the path to a conveyance or storage element overtopped by the design event.
  • Designing to the average condition when the governing condition is the controlling one.
  • Freezing a design before the constructability and access review that would have changed it.
  • Referencing figures, tables, or sources that never appear in the reference list.
  • Carrying an assumption forward after the governing condition changed, without re-checking the result.
  • Reporting numbers without units, or mixing US customary and SI inside a single calculation chain.

Section L

Industry case study

Ellicott City Flash Floods

Ellicott City, Maryland, 2016 and 2018

Official findings

  • Post-event studies attributed extreme flash flooding partly to a small, steep watershed with rapid time of concentration and upstream imperviousness growth not reflected in older drainage models.

Field observations

  • The controlling assumption was documented nowhere in the design record.
  • No independent check existed at the stage where the error entered the work.

Engineering interpretation

  • Interpretation below is student analysis for instructional purposes, not an official finding.
  • Map the failure to a step in your own workflow and state where your process would have caught it.

Lessons learned

  • Watershed delineation and curve numbers must be updated to reflect current land use, not the land use at original design.

Source: Summarize the published investigation; cite it in your reference list. Do not reproduce copyrighted report text.

Section M

FE Civil exam connection

Handbook FE Reference Handbook — water resources engineering section (record the section number from your handbook edition).

Exam topics

Watershed hydrology
Time of concentration

Handbook formulas

  • Tc = (0.007(nL)^0.8)/(P2^0.5 S^0.4)

Weak results here feed your FE Civil Academy weak-area queue for targeted practice.

Question 1 of 2

Score: 0/2

In watershed delineation, which item must be established BEFORE the analysis is run?

Section N

Apply it to your project — Watershed Delineation

Complete this using your own capstone project data. Every field is saved to your project record and routed to your advisor with this module's submission.

Inputs and sources

Every value needs a traceable source.

QuantityValueUnitSource / record

Assumptions and consequences

AssumptionBasisConsequence if wrong

Self-check before submission

Section O

Design challenge

Consulting challenge — Watershed Delineation

Your firm has been retained to deliver the watershed delineation scope for a municipal client on a compressed schedule. Produce the technical position your firm would defend at a public meeting.

Client request: The client wants a defensible recommendation, the basis of design, and an honest statement of what remains unresolved.

Constraints

  • Adopted local code edition governs; no exceptions without written variance.
  • Budget and schedule are fixed; scope changes require change control.
  • Public safety and accessibility requirements are non-negotiable.

Deliverables

  • One-page basis of design
  • Supporting calculation extract
  • Risk and limitation statement

Evaluation

  • Technical correctness
  • Standard compliance
  • Clarity of engineering judgment
  • Honest treatment of uncertainty

Section P

Documentation workspace

Write the report section for this module in the academic editor

Loading editor…
0 words

Section Q

File uploads

Accepted: PDF, DOCX, XLSX, CSV, PNG, JPG, ZIP, SHP, HEC-HMS

No files uploaded yet.

Section R

Deliverable and advisor review

Watershed delineation map with basin parameters (area, CN, Tc) tabulated.

Engineering design
Technical analysis
Code compliance
Calculation quality
Drawings

Submissions route to your assigned faculty advisor and are scored independently by faculty and administrator rubrics.

Reflection

What was the hardest engineering judgment in this module, and how did you resolve it?

Section S

ABET outcome mapping

SO 1
CE-PC2
reinforced

Watershed delineation map with basin parameters (area, CN, Tc) tabulated. with advisor review and dual scoring.

Assessment: Faculty rubric score and administrator rubric score on this module's submission.

Rubric: Engineering design · Target: 70% of students at or above 'meets expectations'.

SO 2
CE-PC2
reinforced

Watershed delineation map with basin parameters (area, CN, Tc) tabulated. with advisor review and dual scoring.

Assessment: Faculty rubric score and administrator rubric score on this module's submission.

Rubric: Engineering design · Target: 70% of students at or above 'meets expectations'.

Section T

References and further study

standard

NRCS TR-55 (Current)

Adopted reference — cite section numbers, do not reproduce text.

template

Watershed Delineation — instructor design procedure

Course template for the calculation package format expected in the final report appendix.

manual

NCEES FE Reference Handbook

Locate the equations used here and note the handbook section for exam recall.

template

Advisor meeting agenda item

Bring the unresolved decision from this module to your next weekly advisor meeting.

Week 4 · Watershed delineation map with basin parameters (area, CN, Tc) tabulated.
© 2026 Dr. Steve Efe. Civil Engineering Capstone Studio. All rights reserved.