Airport Runway Design

Design runway geometry and pavement per FAA Advisory Circular criteria (if applicable to the capstone project).

Section progress

0% of the workflow complete

Highway & Traffic Engineering · Geometric design, traffic analysis, pavement, intersections and roadway safety to AASHTO and MUTCD.

Deliverable: Runway geometric and pavement design summary per FAA AC criteria.

Minimum tables, figures and equations for Airport Runway Design

Tables — at least 6

  • Table — trial sections or sizes considered, with the capacity of each and the selection decision
  • Table — final selected geometry for every element: dimensions, thickness, grade, spacing, elevation
  • Table — slab, beam, column and shear wall schedule with governing demand
  • Table — ultimate limit state check summary: demand, capacity, ratio, pass or fail, governing clause
  • Table — serviceability check summary: deflection, crack width, settlement, freeboard or velocity against its limit
  • Table — factors of safety achieved against the factor required, per failure mode

Figures — at least 4

  • Figure — free body diagram of each isolated element, fully labelled with loads, reactions, dimensions and axes
  • Figure — shear and moment (or pressure and velocity) diagrams for each force-carrying element
  • Figure — dimensioned section or plan of each designed element
  • Figure — capacity versus demand plot, interaction diagram, or rating curve as applicable

Equations — at least 8

  • Equation — equilibrium equations written out for each free body (sum of forces and sum of moments, or continuity and energy)
  • Equation — the internal force relations V(x) and M(x), or the momentum/thrust relation, used to compute each element's demand
  • Equation — the resulting demand at the critical section of each element, with numeric substitution
  • Equation — the capacity expression for each element type, shown with full numeric substitution and units
  • Equation — the sizing criterion that sets the final dimension (for example required area, depth or diameter)
  • Equation — each limit state check written as demand over capacity with numbers substituted
  • Equation — the factor of safety calculation for each failure mode checked
  • Equation — punching shear, drift and deflection checks with limits

Number every table and figure (Table 4.x, Figure 4.x), caption it, and refer to it by number in your text. Number displayed equations and show the substitution with units. These counts are minimums — add whatever else your design needs.

Engineering documentation standard — required in every Chapter 4 subsection

These rules are graded on every subsection. Work that misses them is capped on technical accuracy, exhibits, codes and communication, whatever the quality of the prose.

Code and standard references

  • Every requirement, factor, coefficient, limit and allowable you apply cites the governing document AND the exact section, article or sub-article number — e.g. ACI 318-19 §22.5.5.1, AISC 360-22 Chapter J, Section J3.6, AASHTO LRFD 10th Ed. Article 3.6.1.2.2, ASCE 7-22 §12.8.1, ASTM D2487, state DOT manual section, local stormwater manual chapter.
  • Give the edition or year of every document the first time it appears, then use a consistent short form.
  • Where a code equation is used, quote the equation number (e.g. Eq. 22.5.5.1) next to your displayed equation.
  • Where you depart from a code provision, state the clause you are departing from and the engineering justification.
  • List every code, standard and manual actually used in a Codes and Standards table at the start of the subsection.

Citations for statements

  • Every statement of fact, value taken from elsewhere, material property, soil parameter, rainfall depth, unit cost or published method carries an in-text citation (APA) to its source.
  • Field and lab data cite the report, boring log, gauge, survey file or test number and its date.
  • Manufacturer data cites the product literature and revision date; software results cite the program, version and model file name.
  • Uncited assertions are treated as assumptions and must appear in the assumptions table with a justification.
  • Every in-text citation resolves to a full entry in the reference list.

Step-by-step calculations

  • Structure every calculation the same way: (1) objective, (2) governing code clause, (3) equation in symbolic form with the equation number, (4) definition of each symbol, (5) numerical substitution, (6) result with units, (7) comparison against the limit and the pass/fail statement.
  • Show the substitution line — never jump from the formula to the answer.
  • Number displayed equations sequentially (Eq. 4.1, 4.2, …) and refer to them by number in the text.
  • State the load or flow combination governing each calculation by name.
  • Carry consistent significant figures and round only at the reported result; state the rounding convention once.
  • Present repetitive element checks in a calculation table with one row per element and the same column order throughout.

Free body diagrams and figures

  • Draw a separate free body diagram for each isolated element — no combined sketches standing in for several members.
  • Dimension every FBD: span, depth, thickness, cover, eccentricity, embedment, slope, pipe diameter, wall height — with the dimension lines and values shown.
  • Label every force, pressure, reaction and moment with its symbol, magnitude and units, and show the sign convention and coordinate axes.
  • Show supports and boundary conditions explicitly (pin, roller, fixed, elastic, buoyant, hydrostatic).
  • Accompany each FBD with its shear, moment, thrust, pressure or hydraulic grade diagram at the same scale reference.
  • Number and caption every figure (Figure 4.x) and refer to it by number in the narrative; add a scale or north arrow to plans.

Units and notation

  • Every number in text, tables, figures and equations carries its unit — no bare numbers.
  • Use one unit system throughout (US customary or SI); if both appear, give the converted value in parentheses consistently.
  • Check dimensional homogeneity of each equation and say so — the units of both sides must match.
  • Provide a nomenclature table defining every symbol with its unit.

Checking and verification

  • Every calculation is checked by an independent route — hand check against software, alternative method, order-of-magnitude estimate, or a published worked example — and the check is shown, not just claimed.
  • Report demand-to-capacity ratios and factors of safety against the required values, with the source clause for each required value.
  • Include a verification/checking table: item, method of check, expected, obtained, difference, accept or revise.
  • Sanity-check every result (magnitude, direction, plausibility) and state the conclusion.
  • Record who checked the work and on what date; flag anything still unverified as an open item.
  • State limitations and the range over which the result is valid.

How to complete this section

0 words saved

Do this next: Read the Airport Runway Design lecture and the worked example so you know what "Runway geometric and pavement design summary per FAA AC criteria." has to contain.

Not sure how to start or how much depth is expected? Read the fully written model example for this deliverable first — it shows the structure, tables and level of justification your advisor grades against.

Transportation Design Office — what this workspace teaches

Geometric design, traffic analysis, pavement, intersections and roadway safety to AASHTO and MUTCD.

  • AASHTO Green Book design controls: design speed, functional class, design vehicle
  • Traffic data: AADT, DHV, K and D factors, truck percentage, growth projection
  • Horizontal alignment: curve radius, superelevation, side friction, transitions
  • Vertical alignment: grades, crest and sag curves, K-values
  • Sight distance: stopping, decision, passing and intersection sight distance
  • Cross sections: lane and shoulder widths, side slopes, clear zone
  • Pavement design: ESALs, subgrade support, layer thicknesses (flexible and rigid)
  • Intersection design, roundabouts, turn lanes and capacity
  • Traffic signals: warrants, phasing, cycle length, timing (MUTCD/HCM)
  • Roadway drainage and safety: crash analysis, barriers, clear zone

End-of-term milestones

  • Tuesday, November 17, 2026 — Poster printed and ready. 36 in × 48 in poster finalized and printed one week before the November 24 showcase.
  • Wednesday, November 18, 2026 — Final document package uploaded for scoring. Chapters 4–5, calculation package, drawings and appendices uploaded in the app for advisor scoring.
  • Wednesday, November 18, 2026 — Poster presentation to faculty and industry. Wednesday poster session — printed 36 in × 48 in poster presented in person; industry reviewers score communication and impact.
  • Wednesday, November 25, 2026 — Oral presentation and defense (scored). Scored oral presentation and defense held on Wednesday, November 25.
Week 6
transportation
Transportation

Airport Runway Design

Design runway geometry and pavement per FAA Advisory Circular criteria (if applicable to the capstone project).

Section B

Engineering story

A real project situation that frames this module

Week 6: airport runway design is the item standing between the team and a reviewable roadway geometry, control plan and operational analysis. Design runway geometry and pavement per FAA Advisory Circular criteria (if applicable to the capstone project). Review stalls on a single line: the team cannot show the record behind airport reference code (ARC) and design aircraft selection.

Sizing runway length from a single generic aircraft chart without airport elevation/temperature correction. Because runway length determination from aircraft performance and airport elevation/temperature, the error does not stay local: it is carried into the design of record that drawings, quantities and cost are generated from, and every downstream product inherits it before anyone notices.

Drivers, pedestrians, cyclists, transit riders and the agency that owns the facility carry the consequence. On this module specifically, the exposure runs through runway safety area (RSA), object free area (OFA), and obstacle clearance surfaces, and the cost of correction rises every week the roadway geometry, control plan and operational analysis moves closer to issue.

Decisions the engineer must make

  • What record establishes airport reference code (ARC) and design aircraft selection, and is that record in the project data inventory?
  • Does FAA AC 150/5300-13B (Current), Ch. 3, govern here — and is that the edition adopted by the jurisdiction?
  • What is the acceptance criterion for runway length determination from aircraft performance and airport elevation/temperature, and was it written before the result was known?
  • Is the documented procedure valid for the conditions this project actually presents?
  • If the check fails, does the team revise the roadway geometry, control plan and operational analysis or raise a change request against the locked baseline?
Dense peak-hour traffic queued on an urban arterial at dusk.

Photo 1. Peak-hour demand: the flow rate that drives capacity, delay and level-of-service analysis.

Wikimedia Commons, CC BY 2.0

Section C

Why this matters

Professional

A licensed engineer defending airport runway design cites FAA AC 150/5300-13B (Current), Ch. 3, and shows the record behind each input. Your runway geometric and pavement design summary per faa ac criteria. is reviewed the same way — traceability is assessed before arithmetic.

Technical

Airport reference code (ARC) and design aircraft selection controls the numbers this module hands forward. Runway length determination from aircraft performance and airport elevation/temperature determines whether those numbers remain valid once conditions change.

Safety

The failure mode this module guards against is a geometric or control element that puts drivers in a conflict they cannot resolve. It reaches people through runway pavement design for aircraft gear loading (FAARFIELD), which is why the safety check is recorded explicitly here rather than inferred from a passing strength or performance check.

Economic

The design of record that drawings, quantities and cost are generated from is priced from this work. Quantities, unit costs and schedule float all trace to airport reference code (ARC) and design aircraft selection; a late correction here is paid for as a change order, not a redline.

Environmental

Environmentally, this module fixes vehicle delay emissions, pavement material demand and stormwater from added impervious area. Choosing conservatively without justification is not free — the excess shows up as material, energy and land that the project consumes for no measurable gain.

Community

Everyone who walks, rides or drives the corridor every day inherit whatever this module decides — performance, accessibility, cost of ownership and resilience are set here, not at the ribbon-cutting.

Section D

Learning objectives

By the end of this module you will be able to:

  1. 1.Explain airport reference code (ARC) and design aircraft selection, using this project's own conditions rather than a textbook case.
  2. 2.Evaluate runway length determination from aircraft performance and airport elevation/temperature, using this project's own conditions rather than a textbook case.
  3. 3.Interpret runway safety area (RSA), object free area (OFA), and obstacle clearance surfaces, using this project's own conditions rather than a textbook case.
  4. 4.Apply runway pavement design for aircraft gear loading (FAARFIELD), using this project's own conditions rather than a textbook case.
  5. 5.Apply FAA AC 150/5300-13B (Current), Ch. 3, and cite the section that governs your acceptance decision.
  6. 6.Produce runway geometric and pavement design summary per faa ac criteria. at a standard the DOT design reviewer would accept without a second revision cycle.

Section E

Instructional content

Full lecture notes with figures and governing equations

Reading airport runway design as a practising engineer

Design runway geometry and pavement per FAA Advisory Circular criteria (if applicable to the capstone project). That single sentence hides the substance of the module: airport reference code (ARC) and design aircraft selection, and runway length determination from aircraft performance and airport elevation/temperature. Both must be established from project evidence before anything downstream is credible.

In transportation engineering, this work is the input to the roadway geometry, control plan and operational analysis. Runway safety area (RSA), object free area (OFA), and obstacle clearance surfaces — which is why this page asks you to record the source of every quantity, not just its value. The design of record that drawings, quantities and cost are generated from depends on it.

  • Airport reference code (ARC) and design aircraft selection
  • Runway length determination from aircraft performance and airport elevation/temperature
  • Runway safety area (RSA), object free area (OFA), and obstacle clearance surfaces
  • Runway pavement design for aircraft gear loading (FAARFIELD)
FIGURE 1center, RPCPT1Runway2RSA3OFA4Obstacle clearance surface5Taxiway6Design aircraft
Figure 1. Airport Runway Design — annotated engineering schematic showing the governing quantities carried through this module.Read this figure alongside the theory block: every labelled quantity must appear in your calculation package with a unit and a source.
Dense peak-hour traffic queued on an urban arterial at dusk.

Photo 1. Reading airport runway design as a practising engineer in practice — Peak-hour demand: the flow rate that drives capacity, delay and level-of-service analysis.

Wikimedia Commons, CC BY 2.0

Decision logic: the procedure that replaces a closed-form solution

Airport Runway Design is governed by a documented procedure rather than a single expression, so the decision logic is the deliverable: what you accept, what you reject, and on what evidence. Airport reference code (ARC) and design aircraft selection.

Write the acceptance criterion before you look at the result. Runway length determination from aircraft performance and airport elevation/temperature — recording the criterion afterwards lets it be shaped to fit the number you happened to get.

Dense peak-hour traffic queued on an urban arterial at dusk.

Photo 2. Decision logic: the procedure that replaces a closed-form solution in practice — Peak-hour demand: the flow rate that drives capacity, delay and level-of-service analysis.

Wikimedia Commons, CC BY 2.0

Constraints, adopted standards and the safety case for airport runway design

FAA AC 150/5300-13B (Current), Ch. 3, governs this module: Airport design standards FAA AC 150/5320-6G (Current), Ch. 3, adds the second constraint: Airport pavement design

The safety case is explicit here. The failure mode is a geometric or control element that puts drivers in a conflict they cannot resolve; the people exposed are drivers, pedestrians, cyclists, transit riders and the agency that owns the facility; the control that prevents it is runway pavement design for aircraft gear loading (FAARFIELD) together with an independent check by someone who did not perform the work.

  • Controlling criterion for this module: airport reference code (ARC) and design aircraft selection.
  • Adopted reference: FAA AC 150/5300-13B (Current) — cite Ch. 3 by number.
  • Failure mode guarded: a geometric or control element that puts drivers in a conflict they cannot resolve.
  • Evidence produced: Runway geometric and pavement design summary per FAA AC criteria..
FIGURE 2Confirm inputs and sourcesSelect governing standardAnalyze / designCheck units and equilibriumIndependent checkAccept or revise
Figure 2. Airport Runway Design — professional workflow from inputs through acceptance.The revise loop is normal. Reviewers expect to see it in your version history.
Dense peak-hour traffic queued on an urban arterial at dusk.

Photo 3. Constraints, adopted standards and the safety case for airport runway design in practice — Peak-hour demand: the flow rate that drives capacity, delay and level-of-service analysis.

Wikimedia Commons, CC BY 2.0

Where this method stops being valid

Every method has a domain of validity. State the range of geometry, loading, material behaviour or flow regime over which your approach holds, and state what you would do instead beyond it.

For this project, the boundary you are most likely to push is runway pavement design for aircraft gear loading (FAARFIELD). If you cross it, say so in writing, bound the error, and carry the limitation into your results chapter. A disclosed limitation is professional practice; a silent extrapolation is not.

Dense peak-hour traffic queued on an urban arterial at dusk.

Photo 4. Where this method stops being valid in practice — Peak-hour demand: the flow rate that drives capacity, delay and level-of-service analysis.

Wikimedia Commons, CC BY 2.0

Section F

Engineering workflow

Steps

  1. 1. Assemble the inputs this module needs — airport reference code (ARC) and design aircraft selection; runway length determination from aircraft performance and airport elevation/temperature — each with a unit and a source record.
  2. 2. Confirm FAA AC 150/5300-13B (Current) is the adopted edition and locate Ch. 3.
  3. 3. State the assumptions and the acceptance criterion for airport reference code (ARC) and design aircraft selection.
  4. 4. Execute the documented procedure, recording each judgement and the evidence behind it.
  5. 5. Test the result against runway safety area (RSA), object free area (OFA), and obstacle clearance surfaces.
  6. 6. Audit units and run an order-of-magnitude check by hand before the number leaves your desk.
  7. 7. Obtain an independent check from a teammate who did not perform the work, and record their name and date.
  8. 8. Assemble runway geometric and pavement design summary per faa ac criteria. and submit it to the DOT design reviewer for review.

Decision points

  • Is every input behind airport reference code (ARC) and design aircraft selection traceable? If not — stop and collect the record.
  • Does the result satisfy runway length determination from aircraft performance and airport elevation/temperature? If not — revise the work, never the criterion.
  • Would the correction change the design of record that drawings, quantities and cost are generated from? If yes — raise a change-control request before proceeding.
  • Have you ruled out the most common error on this module — sizing runway length from a single generic aircraft chart without airport elevation/temperature correction?

Quality checklist

  • Documented: airport reference code (ARC) and design aircraft selection
  • Documented: runway length determination from aircraft performance and airport elevation/temperature
  • Documented: runway safety area (RSA), object free area (OFA), and obstacle clearance surfaces
  • FAA AC 150/5300-13B Ch. 3 cited by section number
  • Procedure steps recorded in order with evidence
  • Acceptance criterion recorded before the result
  • Independent check signed and dated
  • Runway geometric and pavement design summary per FAA AC criteria. attached and named per the course convention

Section H

Interactive visualization

Airport Runway Design — step-through

Advance one frame at a time. Each frame adds one engineering decision to the previous state.

Stepwise reveal

Step 1 of 6

Select critical/design aircraft

Section I

Applicable codes and standards

FAA AC 150/5300-13B

Current · Ch. 3

Adopted design/analysis reference governing this module.

Relevance: Airport design standards

Reference the section number and edition in your calculation package. Do not reproduce code text.

FAA AC 150/5320-6G

Current · Ch. 3

Adopted design/analysis reference governing this module.

Relevance: Airport pavement design

Reference the section number and edition in your calculation package. Do not reproduce code text.

Section J

Worked examples

Full engineering solution format

Section K

Common mistakes and how to avoid them

  • Sizing runway length from a single generic aircraft chart without airport elevation/temperature correction
  • Encroaching into the runway safety area with a proposed structure
  • Applying highway pavement layer coefficients to airfield gear loads
  • Treating airport reference code (ARC) and design aircraft selection as a given instead of establishing it from a project record.
  • Producing runway geometric and pavement design summary per faa ac criteria. without showing how runway length determination from aircraft performance and airport elevation/temperature was satisfied.
  • Recording the outcome of this module without recording the judgement and evidence that produced it.
  • Missing runway pavement design for aircraft gear loading (FAARFIELD), which is exactly the path to a geometric or control element that puts drivers in a conflict they cannot resolve.
  • Designing to the average condition when the governing condition is the controlling one.
  • Freezing a design before the constructability and access review that would have changed it.
  • Ignoring constructability: a design that cannot be built safely is not a completed design.
  • Omitting the safety check because the strength check passed.
  • Referencing figures, tables, or sources that never appear in the reference list.

Section L

Industry case study

Documented failure related to airport runway design

A constructed civil works project where this module's decision was made incorrectly or skipped.

Official findings

  • Published investigation identified a breakdown between analysis assumption and constructed condition.

Field observations

  • The controlling assumption was documented nowhere in the design record.
  • No independent check existed at the stage where the error entered the work.

Engineering interpretation

  • Interpretation below is student analysis for instructional purposes, not an official finding.
  • Map the failure to a step in your own workflow and state where your process would have caught it.

Lessons learned

  • Document the assumption, then have someone else check it before it becomes construction.

Source: Summarize the published investigation; cite it in your reference list. Do not reproduce copyrighted report text.

Section M

FE Civil exam connection

Handbook FE Reference Handbook — transportation engineering section (record the section number from your handbook edition).

Exam topics

Airport design

Handbook formulas

    Weak results here feed your FE Civil Academy weak-area queue for targeted practice.

    Question 1 of 2

    Score: 0/2

    In airport runway design, which item must be established BEFORE the analysis is run?

    Section N

    Apply it to your project — Airport Runway Design

    Complete this using your own capstone project data. Every field is saved to your project record and routed to your advisor with this module's submission.

    Inputs and sources

    Every value needs a traceable source.

    QuantityValueUnitSource / record

    Assumptions and consequences

    AssumptionBasisConsequence if wrong

    Self-check before submission

    Section O

    Design challenge

    Consulting challenge — Airport Runway Design

    Your firm has been retained to deliver the airport runway design scope for a municipal client on a compressed schedule. Produce the technical position your firm would defend at a public meeting.

    Client request: The client wants a defensible recommendation, the basis of design, and an honest statement of what remains unresolved.

    Constraints

    • Adopted local code edition governs; no exceptions without written variance.
    • Budget and schedule are fixed; scope changes require change control.
    • Public safety and accessibility requirements are non-negotiable.

    Deliverables

    • One-page basis of design
    • Supporting calculation extract
    • Risk and limitation statement

    Evaluation

    • Technical correctness
    • Standard compliance
    • Clarity of engineering judgment
    • Honest treatment of uncertainty

    Section P

    Documentation workspace

    Write the report section for this module in the academic editor

    Loading editor…
    0 words

    Section Q

    File uploads

    Accepted: PDF, DOCX, XLSX, CSV, PNG, JPG, ZIP, DWG, DXF

    No files uploaded yet.

    Section R

    Deliverable and advisor review

    Runway geometric and pavement design summary per FAA AC criteria.

    Engineering design
    Technical analysis
    Code compliance
    Calculation quality
    Drawings

    Submissions route to your assigned faculty advisor and are scored independently by faculty and administrator rubrics.

    Reflection

    What was the hardest engineering judgment in this module, and how did you resolve it?

    Section S

    ABET outcome mapping

    SO 1
    CE-PC2
    reinforced

    Runway geometric and pavement design summary per FAA AC criteria. with advisor review and dual scoring.

    Assessment: Faculty rubric score and administrator rubric score on this module's submission.

    Rubric: Engineering design · Target: 70% of students at or above 'meets expectations'.

    SO 2
    CE-PC2
    reinforced

    Runway geometric and pavement design summary per FAA AC criteria. with advisor review and dual scoring.

    Assessment: Faculty rubric score and administrator rubric score on this module's submission.

    Rubric: Engineering design · Target: 70% of students at or above 'meets expectations'.

    Section T

    References and further study

    standard

    FAA AC 150/5300-13B (Current)

    Adopted reference — cite section numbers, do not reproduce text.

    standard

    FAA AC 150/5320-6G (Current)

    Adopted reference — cite section numbers, do not reproduce text.

    template

    Airport Runway Design — instructor design procedure

    Course template for the calculation package format expected in the final report appendix.

    manual

    NCEES FE Reference Handbook

    Locate the equations used here and note the handbook section for exam recall.

    template

    Advisor meeting agenda item

    Bring the unresolved decision from this module to your next weekly advisor meeting.

    Week 6 · Runway geometric and pavement design summary per FAA AC criteria.