Skip to content
CEGR 493
Design
Week 5
technology
Modeling & Simulation Center
Capstone II dashboard

Clash Detection

Runs systematic clash detection on the coordinated model and documents resolution of hard and soft clashes.

Section progress

0% of the workflow complete

Computational Engineering · Build, calibrate, verify and validate the numerical model that supports your design decisions.

Deliverable: Clash detection report with issue log, closure rate, and outstanding-issue escalation plan.

Minimum tables, figures and equations for Clash Detection

Tables — at least 6

  • Table — trial sections or sizes considered, with the capacity of each and the selection decision
  • Table — final selected geometry for every element: dimensions, thickness, grade, spacing, elevation
  • Table — slab, beam, column and shear wall schedule with governing demand
  • Table — ultimate limit state check summary: demand, capacity, ratio, pass or fail, governing clause
  • Table — serviceability check summary: deflection, crack width, settlement, freeboard or velocity against its limit
  • Table — factors of safety achieved against the factor required, per failure mode

Figures — at least 4

  • Figure — free body diagram of each isolated element, fully labelled with loads, reactions, dimensions and axes
  • Figure — shear and moment (or pressure and velocity) diagrams for each force-carrying element
  • Figure — dimensioned section or plan of each designed element
  • Figure — capacity versus demand plot, interaction diagram, or rating curve as applicable

Equations — at least 8

  • Equation — equilibrium equations written out for each free body (sum of forces and sum of moments, or continuity and energy)
  • Equation — the internal force relations V(x) and M(x), or the momentum/thrust relation, used to compute each element's demand
  • Equation — the resulting demand at the critical section of each element, with numeric substitution
  • Equation — the capacity expression for each element type, shown with full numeric substitution and units
  • Equation — the sizing criterion that sets the final dimension (for example required area, depth or diameter)
  • Equation — each limit state check written as demand over capacity with numbers substituted
  • Equation — the factor of safety calculation for each failure mode checked
  • Equation — punching shear, drift and deflection checks with limits

Number every table and figure (Table 4.x, Figure 4.x), caption it, and refer to it by number in your text. Number displayed equations and show the substitution with units. These counts are minimums — add whatever else your design needs.

Engineering documentation standard — required in every Chapter 4 subsection

These rules are graded on every subsection. Work that misses them is capped on technical accuracy, exhibits, codes and communication, whatever the quality of the prose.

Code and standard references

  • Every requirement, factor, coefficient, limit and allowable you apply cites the governing document AND the exact section, article or sub-article number — e.g. ACI 318-19 §22.5.5.1, AISC 360-22 Chapter J, Section J3.6, AASHTO LRFD 10th Ed. Article 3.6.1.2.2, ASCE 7-22 §12.8.1, ASTM D2487, state DOT manual section, local stormwater manual chapter.
  • Give the edition or year of every document the first time it appears, then use a consistent short form.
  • Where a code equation is used, quote the equation number (e.g. Eq. 22.5.5.1) next to your displayed equation.
  • Where you depart from a code provision, state the clause you are departing from and the engineering justification.
  • List every code, standard and manual actually used in a Codes and Standards table at the start of the subsection.

Citations for statements

  • Every statement of fact, value taken from elsewhere, material property, soil parameter, rainfall depth, unit cost or published method carries an in-text citation (APA) to its source.
  • Field and lab data cite the report, boring log, gauge, survey file or test number and its date.
  • Manufacturer data cites the product literature and revision date; software results cite the program, version and model file name.
  • Uncited assertions are treated as assumptions and must appear in the assumptions table with a justification.
  • Every in-text citation resolves to a full entry in the reference list.

Step-by-step calculations

  • Structure every calculation the same way: (1) objective, (2) governing code clause, (3) equation in symbolic form with the equation number, (4) definition of each symbol, (5) numerical substitution, (6) result with units, (7) comparison against the limit and the pass/fail statement.
  • Show the substitution line — never jump from the formula to the answer.
  • Number displayed equations sequentially (Eq. 4.1, 4.2, …) and refer to them by number in the text.
  • State the load or flow combination governing each calculation by name.
  • Carry consistent significant figures and round only at the reported result; state the rounding convention once.
  • Present repetitive element checks in a calculation table with one row per element and the same column order throughout.

Free body diagrams and figures

  • Draw a separate free body diagram for each isolated element — no combined sketches standing in for several members.
  • Dimension every FBD: span, depth, thickness, cover, eccentricity, embedment, slope, pipe diameter, wall height — with the dimension lines and values shown.
  • Label every force, pressure, reaction and moment with its symbol, magnitude and units, and show the sign convention and coordinate axes.
  • Show supports and boundary conditions explicitly (pin, roller, fixed, elastic, buoyant, hydrostatic).
  • Accompany each FBD with its shear, moment, thrust, pressure or hydraulic grade diagram at the same scale reference.
  • Number and caption every figure (Figure 4.x) and refer to it by number in the narrative; add a scale or north arrow to plans.

Units and notation

  • Every number in text, tables, figures and equations carries its unit — no bare numbers.
  • Use one unit system throughout (US customary or SI); if both appear, give the converted value in parentheses consistently.
  • Check dimensional homogeneity of each equation and say so — the units of both sides must match.
  • Provide a nomenclature table defining every symbol with its unit.

Checking and verification

  • Every calculation is checked by an independent route — hand check against software, alternative method, order-of-magnitude estimate, or a published worked example — and the check is shown, not just claimed.
  • Report demand-to-capacity ratios and factors of safety against the required values, with the source clause for each required value.
  • Include a verification/checking table: item, method of check, expected, obtained, difference, accept or revise.
  • Sanity-check every result (magnitude, direction, plausibility) and state the conclusion.
  • Record who checked the work and on what date; flag anything still unverified as an open item.
  • State limitations and the range over which the result is valid.

How to complete this section

0 words saved

Do this next: Read the Clash Detection lecture and the worked example so you know what "Clash detection report with issue log, closure rate, and outstanding-issue escalation plan." has to contain.

Not sure how to start or how much depth is expected? Read the fully written model example for this deliverable first — it shows the structure, tables and level of justification your advisor grades against.

Modeling & Simulation Center — what this workspace teaches

Build, calibrate, verify and validate the numerical model that supports your design decisions.

  • Selecting analysis software for the engineering question (STAAD, SAP2000, ETABS, HEC-RAS, OpenRoads, Civil3D, ArcGIS, MATLAB, Python)
  • Model geometry idealization and simplification
  • Boundary conditions, supports, restraints and their effect on results
  • Load application and load-case management in software
  • Mesh and element selection; convergence studies
  • Model calibration against measured or benchmark data
  • Sensitivity analysis of governing input parameters
  • Verification (solving the equations right) vs. validation (solving the right equations)
  • Exporting, documenting and archiving model results

End-of-term milestones

  • Tuesday, November 17, 2026 — Poster printed and ready. 36 in × 48 in poster finalized and printed one week before the November 24 showcase.
  • Wednesday, November 18, 2026 — Final document package uploaded for scoring. Chapters 4–5, calculation package, drawings and appendices uploaded in the app for advisor scoring.
  • Wednesday, November 18, 2026 — Poster presentation to faculty and industry. Wednesday poster session — printed 36 in × 48 in poster presented in person; industry reviewers score communication and impact.
  • Wednesday, November 25, 2026 — Oral presentation and defense (scored). Scored oral presentation and defense held on Wednesday, November 25.
Week 5
technology
Environmental, Materials, Construction and Technology

Clash Detection

Runs systematic clash detection on the coordinated model and documents resolution of hard and soft clashes.

Section B

Engineering story

A real project situation that frames this module

The team opens week 5 believing clash detection is a formality, because the proposal treated it in a single sentence. Runs systematic clash detection on the coordinated model and documents resolution of hard and soft clashes. The first review question is not about arithmetic — it is where the basis for hard clash (geometric overlap) vs came from.

Running clash detection once at the end instead of iteratively through design development. Because clash detection tolerance settings and grid/zone-based test scoping, the error does not stay local: it is carried into the design of record that drawings, quantities and cost are generated from, and every downstream product inherits it before anyone notices.

Every downstream discipline that inherits the model and the engineer who seals it carry the consequence. On this module specifically, the exposure runs through clash prioritization by discipline, cost impact, and schedule impact, and the cost of correction rises every week the model, dataset and documented computational workflow moves closer to issue.

Decisions the engineer must make

  • What record establishes hard clash (geometric overlap) vs, and is that record in the project data inventory?
  • Does ISO 19650-2 (2018), Information production methods and procedures, govern here — and is that the edition adopted by the jurisdiction?
  • What is the acceptance criterion for clash detection tolerance settings and grid/zone-based test scoping, and was it written before the result was known?
  • Is Clash closure rate at milestone: CR = Nresolved / Ntotal × 100% valid over the parameter range this project actually occupies?
  • If the check fails, does the team revise the model, dataset and documented computational workflow or raise a change request against the locked baseline?
Three engineers in hard hats and safety vests reviewing drawings on a truck tailgate.

Photo 1. Field review: the conversation in which a scope, a constraint or a decision is actually settled.

Capstone Studio instructional photograph

Section C

Why this matters

Professional

A licensed engineer defending clash detection cites ISO 19650-2 (2018), Information production methods and procedures, and shows the record behind each input. Your clash detection report with issue log, closure rate, and outstanding-issue escalation plan. is reviewed the same way — traceability is assessed before arithmetic.

Technical

Hard clash (geometric overlap) vs is what makes Clash closure rate at milestone: CR = Nresolved / Ntotal × 100% usable on this project rather than a formula copied from a reference. Get it wrong and every quantity derived from it is wrong by the same factor.

Safety

The failure mode this module guards against is an unverified model output accepted as an engineering result. It reaches people through re-run and regression checking after model updates, which is why the safety check is recorded explicitly here rather than inferred from a passing strength or performance check.

Economic

The design of record that drawings, quantities and cost are generated from is priced from this work. Quantities, unit costs and schedule float all trace to hard clash (geometric overlap) vs; a late correction here is paid for as a change order, not a redline.

Environmental

Environmentally, this module fixes decisions on quantity and material that the model silently drives. Choosing conservatively without justification is not free — the excess shows up as material, energy and land that the project consumes for no measurable gain.

Community

Clash detection must extend beyond geometric MEP/structure clashes to include structural–geotechnical interface assumptions. The public that depends on results no one outside the modelling team can reproduce live with that outcome long after the semester ends.

Section D

Learning objectives

By the end of this module you will be able to:

  1. 1.Analyze hard clash (geometric overlap) vs, using this project's own conditions rather than a textbook case.
  2. 2.Explain clash detection tolerance settings and grid/zone-based test scoping, using this project's own conditions rather than a textbook case.
  3. 3.Interpret clash prioritization by discipline, cost impact, and schedule impact, using this project's own conditions rather than a textbook case.
  4. 4.Compare issue-tracking workflow, using this project's own conditions rather than a textbook case.
  5. 5.Compute the governing quantity from Clash closure rate at milestone: CR = Nresolved / Ntotal × 100%, with a unit audit on every term.
  6. 6.Apply ISO 19650-2 (2018), Information production methods and procedures, and cite the section that governs your acceptance decision.
  7. 7.Reproduce the worked example for at the 50% CD milestone, 120 clashes have been identified across all systems and defend the interpretation of the result.
  8. 8.Produce clash detection report with issue log, closure rate, and outstanding-issue escalation plan. at a standard the independent model checker would accept without a second revision cycle.

Section E

Instructional content

Full lecture notes with figures and governing equations

Clash Detection — what the work actually is

Runs systematic clash detection on the coordinated model and documents resolution of hard and soft clashes. That single sentence hides the substance of the module: hard clash (geometric overlap) vs, and clash detection tolerance settings and grid/zone-based test scoping. Both must be established from project evidence before anything downstream is credible.

In engineering computation and digital delivery, this work is the input to the model, dataset and documented computational workflow. Clash prioritization by discipline, cost impact, and schedule impact — which is why this page asks you to record the source of every quantity, not just its value. The design of record that drawings, quantities and cost are generated from depends on it.

  • Hard clash (geometric overlap) vs. soft clash (clearance/tolerance violation) vs. workflow clash (sequencing)
  • Clash detection tolerance settings and grid/zone-based test scoping
  • Clash prioritization by discipline, cost impact, and schedule impact
  • Issue-tracking workflow: identify, assign, resolve, verify, close
  • Re-run and regression checking after model updates
FIGURE 1Clash IDDiscipline pair1Clash ID2Discipline pair3Severity4Assigned to5Status6Resolution date
Figure 1. Clash Detection — annotated engineering schematic showing the governing quantities carried through this module.Read this figure alongside the theory block: every labelled quantity must appear in your calculation package with a unit and a source.
Concrete cylinder under axial load in a compression testing machine.

Photo 1. Clash Detection — what the work actually is in practice — Compression test on a concrete cylinder: the measurement behind every f′c used in design.

Wikimedia Commons, public domain

Governing relationships and how they are applied here

The relationships below govern clash detection. Clash closure rate at milestone: CR = Nresolved / Ntotal × 100% — each is valid only inside the parameter range this project occupies, so state that range before substituting.

Clash detection tolerance settings and grid/zone-based test scoping sets the values you place into these expressions. Any code-prescribed factor must match ISO 19650-2 (2018); a factor lifted from a different edition silently changes the answer.

Clash closure rate at milestone: CR = Nresolved / Ntotal × 100%

  • Nresolved = clashes closed
  • Ntotal = clashes identified to date
Three engineers in hard hats and safety vests reviewing drawings on a truck tailgate.

Photo 2. Governing relationships and how they are applied here in practice — Field review: the conversation in which a scope, a constraint or a decision is actually settled.

Capstone Studio instructional photograph

Constraints, adopted standards and the safety case for clash detection

ISO 19650-2 (2018), Information production methods and procedures, governs this module: Governs clash detection as part of the CDE workflow BSRIA BG 6 (2020 Ed.), BIM coordination protocol, adds the second constraint: Reference practice for clash detection tolerance settings

The safety case is explicit here. The failure mode is an unverified model output accepted as an engineering result; the people exposed are every downstream discipline that inherits the model and the engineer who seals it; the control that prevents it is re-run and regression checking after model updates together with an independent check by someone who did not perform the work.

  • Controlling criterion for this module: hard clash (geometric overlap) vs.
  • Adopted reference: ISO 19650-2 (2018) — cite Information production methods and procedures by number.
  • Failure mode guarded: an unverified model output accepted as an engineering result.
  • Evidence produced: Clash detection report with issue log, closure rate, and outstanding-issue escalation plan..
FIGURE 2Confirm inputs and sourcesSelect governing standardAnalyze / designCheck units and equilibriumIndependent checkAccept or revise
Figure 2. Clash Detection — professional workflow from inputs through acceptance.The revise loop is normal. Reviewers expect to see it in your version history.
Three engineers in hard hats and safety vests reviewing drawings on a truck tailgate.

Photo 3. Constraints, adopted standards and the safety case for clash detection in practice — Field review: the conversation in which a scope, a constraint or a decision is actually settled.

Capstone Studio instructional photograph

Where this method stops being valid

The worked example — at the 50% CD milestone, 120 clashes have been identified across all systems — holds only while its assumptions hold. 80% closure at 50% CD is behind the typical target of ~95% at that milestone; escalate the remaining 24 clashes before proceeding to 90% CD. Outside that envelope the arithmetic still returns a number, and the number is wrong in a way no unit check will catch.

For this project, the boundary you are most likely to push is re-run and regression checking after model updates. If you cross it, say so in writing, bound the error, and carry the limitation into your results chapter. A disclosed limitation is professional practice; a silent extrapolation is not.

Three engineers in hard hats and safety vests reviewing drawings on a truck tailgate.

Photo 4. Where this method stops being valid in practice — Field review: the conversation in which a scope, a constraint or a decision is actually settled.

Capstone Studio instructional photograph

Section F

Engineering workflow

Steps

  1. 1. Assemble the inputs this module needs — hard clash (geometric overlap) vs; clash detection tolerance settings and grid/zone-based test scoping — each with a unit and a source record.
  2. 2. Confirm ISO 19650-2 (2018) is the adopted edition and locate Information production methods and procedures.
  3. 3. State the assumptions and the acceptance criterion for hard clash (geometric overlap) vs.
  4. 4. Evaluate Clash closure rate at milestone: CR = Nresolved / Ntotal × 100% term by term, carrying one extra significant figure.
  5. 5. Test the result against clash prioritization by discipline, cost impact, and schedule impact.
  6. 6. Audit units and run an order-of-magnitude check by hand before the number leaves your desk.
  7. 7. Obtain an independent check from a teammate who did not perform the work, and record their name and date.
  8. 8. Assemble clash detection report with issue log, closure rate, and outstanding-issue escalation plan. and submit it to the independent model checker for review.

Decision points

  • Is every input behind hard clash (geometric overlap) vs traceable? If not — stop and collect the record.
  • Does the result satisfy clash detection tolerance settings and grid/zone-based test scoping? If not — revise the work, never the criterion.
  • Would the correction change the design of record that drawings, quantities and cost are generated from? If yes — raise a change-control request before proceeding.
  • Have you ruled out the most common error on this module — running clash detection once at the end instead of iteratively through design development?

Quality checklist

  • Documented: hard clash (geometric overlap) vs
  • Documented: clash detection tolerance settings and grid/zone-based test scoping
  • Documented: clash prioritization by discipline, cost impact, and schedule impact
  • ISO 19650-2 Information production methods and procedures cited by section number
  • Units audited on every expression
  • Acceptance criterion recorded before the result
  • Independent check signed and dated
  • Clash detection report with issue log, closure rate, and outstanding-issue escalation plan. attached and named per the course convention

Section H

Interactive visualization

Clash Detection — step-through

Advance one frame at a time. Each frame adds one engineering decision to the previous state.

Review cycle

Step 1 of 6

Scope the clash test by zone and discipline pair.

Section I

Applicable codes and standards

ISO 19650-2

2018 · Information production methods and procedures

Adopted design/analysis reference governing this module.

Relevance: Governs clash detection as part of the CDE workflow

Reference the section number and edition in your calculation package. Do not reproduce code text.

BSRIA BG 6

2020 Ed. · BIM coordination protocol

Adopted design/analysis reference governing this module.

Relevance: Reference practice for clash detection tolerance settings

Reference the section number and edition in your calculation package. Do not reproduce code text.

Section J

Worked examples

Full engineering solution format

Section K

Common mistakes and how to avoid them

  • Running clash detection once at the end instead of iteratively through design development.
  • Not distinguishing hard clashes requiring redesign from soft clashes needing only clearance notes.
  • Closing a clash in the tracker without verifying it in the updated model.
  • Treating hard clash (geometric overlap) vs as a given instead of establishing it from a project record.
  • Producing clash detection report with issue log, closure rate, and outstanding-issue escalation plan. without showing how clash detection tolerance settings and grid/zone-based test scoping was satisfied.
  • Substituting into Clash closure rate at milestone: CR = Nresolved / Ntotal × 100% outside the range where it is valid, and reporting the number anyway.
  • Missing re-run and regression checking after model updates, which is exactly the path to an unverified model output accepted as an engineering result.
  • Designing to the average condition when the governing condition is the controlling one.
  • Freezing a design before the constructability and access review that would have changed it.
  • Citing the wrong edition of a standard, or citing a standard that does not govern the jurisdiction.
  • Leaving boundary conditions undefined so the model is not reproducible by an independent checker.
  • Using inputs that no field record, laboratory report, or published source supports.

Section L

Industry case study

Millennium Tower Settlement (San Francisco)

58-story residential tower, SF

Official findings

  • Ongoing litigation and forensic review identified coordination gaps between structural and geotechnical models that were not caught by design-phase reviews.

Field observations

  • The controlling assumption was documented nowhere in the design record.
  • No independent check existed at the stage where the error entered the work.

Engineering interpretation

  • Interpretation below is student analysis for instructional purposes, not an official finding.
  • Map the failure to a step in your own workflow and state where your process would have caught it.

Lessons learned

  • Clash detection must extend beyond geometric MEP/structure clashes to include structural–geotechnical interface assumptions.

Source: Summarize the published investigation; cite it in your reference list. Do not reproduce copyrighted report text.

Section M

FE Civil exam connection

Handbook FE Reference Handbook — engineering computation and digital delivery section (record the section number from your handbook edition).

Exam topics

Construction management

Handbook formulas

  • Clash closure rate

Weak results here feed your FE Civil Academy weak-area queue for targeted practice.

Question 1 of 2

Score: 0/2

In clash detection, which item must be established BEFORE the analysis is run?

Section N

Apply it to your project — Clash Detection

Complete this using your own capstone project data. Every field is saved to your project record and routed to your advisor with this module's submission.

Inputs and sources

Every value needs a traceable source.

QuantityValueUnitSource / record

Assumptions and consequences

AssumptionBasisConsequence if wrong

Self-check before submission

Section O

Design challenge

Consulting challenge — Clash Detection

Your firm has been retained to deliver the clash detection scope for a municipal client on a compressed schedule. Produce the technical position your firm would defend at a public meeting.

Client request: The client wants a defensible recommendation, the basis of design, and an honest statement of what remains unresolved.

Constraints

  • Adopted local code edition governs; no exceptions without written variance.
  • Budget and schedule are fixed; scope changes require change control.
  • Public safety and accessibility requirements are non-negotiable.

Deliverables

  • One-page basis of design
  • Supporting calculation extract
  • Risk and limitation statement

Evaluation

  • Technical correctness
  • Standard compliance
  • Clarity of engineering judgment
  • Honest treatment of uncertainty

Section P

Documentation workspace

Write the report section for this module in the academic editor

Loading editor…
0 words

Section Q

File uploads

Accepted: PDF, DOCX, XLSX, CSV, PNG, JPG, ZIP

No files uploaded yet.

Section R

Deliverable and advisor review

Clash detection report with issue log, closure rate, and outstanding-issue escalation plan.

Engineering design
Technical analysis
Code compliance
Calculation quality
Drawings

Submissions route to your assigned faculty advisor and are scored independently by faculty and administrator rubrics.

Reflection

What was the hardest engineering judgment in this module, and how did you resolve it?

Section S

ABET outcome mapping

SO 5
CE-PC6
reinforced

Clash detection report with issue log, closure rate, and outstanding-issue escalation plan. with advisor review and dual scoring.

Assessment: Faculty rubric score and administrator rubric score on this module's submission.

Rubric: Engineering design · Target: 70% of students at or above 'meets expectations'.

Section T

References and further study

standard

ISO 19650-2 (2018)

Adopted reference — cite section numbers, do not reproduce text.

standard

BSRIA BG 6 (2020 Ed.)

Adopted reference — cite section numbers, do not reproduce text.

template

Clash Detection — instructor design procedure

Course template for the calculation package format expected in the final report appendix.

manual

NCEES FE Reference Handbook

Locate the equations used here and note the handbook section for exam recall.

template

Advisor meeting agenda item

Bring the unresolved decision from this module to your next weekly advisor meeting.

Week 5 · Clash detection report with issue log, closure rate, and outstanding-issue escalation plan.
© 2026 Dr. Steve Efe. Civil Engineering Capstone Studio. All rights reserved.