Skip to content
CEGR 493
Design
Week 5
general
Environmental Compliance Studio
Capstone II dashboard

Design Alternatives

Develops and compares at least two viable design alternatives against the project's governing criteria before selecting a preferred alternative.

Section progress

0% of the workflow complete

Environmental Engineering · Impact assessment, permitting, water and air quality, noise, waste and mitigation.

Deliverable: Alternatives analysis memo with weighted comparison, value calculation, and documented selection rationale.

Minimum tables, figures and equations for Design Alternatives

Tables — at least 6

  • Table — trial sections or sizes considered, with the capacity of each and the selection decision
  • Table — final selected geometry for every element: dimensions, thickness, grade, spacing, elevation
  • Table — slab, beam, column and shear wall schedule with governing demand
  • Table — ultimate limit state check summary: demand, capacity, ratio, pass or fail, governing clause
  • Table — serviceability check summary: deflection, crack width, settlement, freeboard or velocity against its limit
  • Table — factors of safety achieved against the factor required, per failure mode

Figures — at least 4

  • Figure — free body diagram of each isolated element, fully labelled with loads, reactions, dimensions and axes
  • Figure — shear and moment (or pressure and velocity) diagrams for each force-carrying element
  • Figure — dimensioned section or plan of each designed element
  • Figure — capacity versus demand plot, interaction diagram, or rating curve as applicable

Equations — at least 8

  • Equation — equilibrium equations written out for each free body (sum of forces and sum of moments, or continuity and energy)
  • Equation — the internal force relations V(x) and M(x), or the momentum/thrust relation, used to compute each element's demand
  • Equation — the resulting demand at the critical section of each element, with numeric substitution
  • Equation — the capacity expression for each element type, shown with full numeric substitution and units
  • Equation — the sizing criterion that sets the final dimension (for example required area, depth or diameter)
  • Equation — each limit state check written as demand over capacity with numbers substituted
  • Equation — the factor of safety calculation for each failure mode checked
  • Equation — punching shear, drift and deflection checks with limits

Number every table and figure (Table 4.x, Figure 4.x), caption it, and refer to it by number in your text. Number displayed equations and show the substitution with units. These counts are minimums — add whatever else your design needs.

Engineering documentation standard — required in every Chapter 4 subsection

These rules are graded on every subsection. Work that misses them is capped on technical accuracy, exhibits, codes and communication, whatever the quality of the prose.

Code and standard references

  • Every requirement, factor, coefficient, limit and allowable you apply cites the governing document AND the exact section, article or sub-article number — e.g. ACI 318-19 §22.5.5.1, AISC 360-22 Chapter J, Section J3.6, AASHTO LRFD 10th Ed. Article 3.6.1.2.2, ASCE 7-22 §12.8.1, ASTM D2487, state DOT manual section, local stormwater manual chapter.
  • Give the edition or year of every document the first time it appears, then use a consistent short form.
  • Where a code equation is used, quote the equation number (e.g. Eq. 22.5.5.1) next to your displayed equation.
  • Where you depart from a code provision, state the clause you are departing from and the engineering justification.
  • List every code, standard and manual actually used in a Codes and Standards table at the start of the subsection.

Citations for statements

  • Every statement of fact, value taken from elsewhere, material property, soil parameter, rainfall depth, unit cost or published method carries an in-text citation (APA) to its source.
  • Field and lab data cite the report, boring log, gauge, survey file or test number and its date.
  • Manufacturer data cites the product literature and revision date; software results cite the program, version and model file name.
  • Uncited assertions are treated as assumptions and must appear in the assumptions table with a justification.
  • Every in-text citation resolves to a full entry in the reference list.

Step-by-step calculations

  • Structure every calculation the same way: (1) objective, (2) governing code clause, (3) equation in symbolic form with the equation number, (4) definition of each symbol, (5) numerical substitution, (6) result with units, (7) comparison against the limit and the pass/fail statement.
  • Show the substitution line — never jump from the formula to the answer.
  • Number displayed equations sequentially (Eq. 4.1, 4.2, …) and refer to them by number in the text.
  • State the load or flow combination governing each calculation by name.
  • Carry consistent significant figures and round only at the reported result; state the rounding convention once.
  • Present repetitive element checks in a calculation table with one row per element and the same column order throughout.

Free body diagrams and figures

  • Draw a separate free body diagram for each isolated element — no combined sketches standing in for several members.
  • Dimension every FBD: span, depth, thickness, cover, eccentricity, embedment, slope, pipe diameter, wall height — with the dimension lines and values shown.
  • Label every force, pressure, reaction and moment with its symbol, magnitude and units, and show the sign convention and coordinate axes.
  • Show supports and boundary conditions explicitly (pin, roller, fixed, elastic, buoyant, hydrostatic).
  • Accompany each FBD with its shear, moment, thrust, pressure or hydraulic grade diagram at the same scale reference.
  • Number and caption every figure (Figure 4.x) and refer to it by number in the narrative; add a scale or north arrow to plans.

Units and notation

  • Every number in text, tables, figures and equations carries its unit — no bare numbers.
  • Use one unit system throughout (US customary or SI); if both appear, give the converted value in parentheses consistently.
  • Check dimensional homogeneity of each equation and say so — the units of both sides must match.
  • Provide a nomenclature table defining every symbol with its unit.

Checking and verification

  • Every calculation is checked by an independent route — hand check against software, alternative method, order-of-magnitude estimate, or a published worked example — and the check is shown, not just claimed.
  • Report demand-to-capacity ratios and factors of safety against the required values, with the source clause for each required value.
  • Include a verification/checking table: item, method of check, expected, obtained, difference, accept or revise.
  • Sanity-check every result (magnitude, direction, plausibility) and state the conclusion.
  • Record who checked the work and on what date; flag anything still unverified as an open item.
  • State limitations and the range over which the result is valid.

How to complete this section

0 words saved

Do this next: Read the Design Alternatives lecture and the worked example so you know what "Alternatives analysis memo with weighted comparison, value calculation, and documented selection rationale." has to contain.

Not sure how to start or how much depth is expected? Read the fully written model example for this deliverable first — it shows the structure, tables and level of justification your advisor grades against.

Environmental Compliance Studio — what this workspace teaches

Impact assessment, permitting, water and air quality, noise, waste and mitigation.

  • NEPA process: categorical exclusion, EA, EIS and public involvement
  • EPA and state permitting: NPDES, Section 404, SWPPP
  • Water quality standards, sampling and impairment
  • Air quality: criteria pollutants, construction emissions, conformity
  • Noise assessment, receptors and abatement criteria
  • Solid and hazardous waste handling on construction projects
  • Sustainability frameworks (Envision, LEED) and life-cycle thinking
  • Mitigation planning, monitoring and compliance documentation

End-of-term milestones

  • Tuesday, November 17, 2026 — Poster printed and ready. 36 in × 48 in poster finalized and printed one week before the November 24 showcase.
  • Wednesday, November 18, 2026 — Final document package uploaded for scoring. Chapters 4–5, calculation package, drawings and appendices uploaded in the app for advisor scoring.
  • Wednesday, November 18, 2026 — Poster presentation to faculty and industry. Wednesday poster session — printed 36 in × 48 in poster presented in person; industry reviewers score communication and impact.
  • Wednesday, November 25, 2026 — Oral presentation and defense (scored). Scored oral presentation and defense held on Wednesday, November 25.
Week 5
general
Environmental, Materials, Construction and Technology

Design Alternatives

Develops and compares at least two viable design alternatives against the project's governing criteria before selecting a preferred alternative.

Section B

Engineering story

A real project situation that frames this module

Week 5: design alternatives is the item standing between the team and a reviewable project record. Develops and compares at least two viable design alternatives against the project's governing criteria before selecting a preferred alternative. Review stalls on a single line: the team cannot show the record behind alternatives analysis framework.

Presenting only one 'alternative' dressed up as a comparison. Because weighted decision matrix with documented scoring rationale, the error does not stay local: it is carried into the design of record that drawings, quantities and cost are generated from, and every downstream product inherits it before anyone notices.

The owner, the reviewing agency and the engineer of record carry the consequence. On this module specifically, the exposure runs through value engineering — function analysis and cost-function ratio, and the cost of correction rises every week the project record moves closer to issue.

Decisions the engineer must make

  • What record establishes alternatives analysis framework, and is that record in the project data inventory?
  • Does SAVE International Value Methodology Standard (2020), Function analysis and VE job plan, govern here — and is that the edition adopted by the jurisdiction?
  • What is the acceptance criterion for weighted decision matrix with documented scoring rationale, and was it written before the result was known?
  • Is Value: V = Function / Cost valid over the parameter range this project actually occupies?
  • If the check fails, does the team revise the project record or raise a change request against the locked baseline?
Interior of a steel and glass pedestrian bridge showing the structural framing.

Photo 1. Structural framing of a pedestrian bridge: members, connections and the load path a designer must trace.

Wikimedia Commons, CC BY-SA 4.0

Section C

Why this matters

Professional

A licensed engineer defending design alternatives cites SAVE International Value Methodology Standard (2020), Function analysis and VE job plan, and shows the record behind each input. Your alternatives analysis memo with weighted comparison, value calculation, and documented selection rationale. is reviewed the same way — traceability is assessed before arithmetic.

Technical

Alternatives analysis framework is what makes Value: V = Function / Cost usable on this project rather than a formula copied from a reference. Get it wrong and every quantity derived from it is wrong by the same factor.

Safety

The failure mode this module guards against is a decision made without a traceable basis. It reaches people through documentation of the rejected alternative's rationale for the record, which is why the safety check is recorded explicitly here rather than inferred from a passing strength or performance check.

Economic

The design of record that drawings, quantities and cost are generated from is priced from this work. Quantities, unit costs and schedule float all trace to alternatives analysis framework; a late correction here is paid for as a change order, not a redline.

Environmental

Environmentally, this module fixes material use, land disturbance and the waste stream generated by rework. Choosing conservatively without justification is not free — the excess shows up as material, energy and land that the project consumes for no measurable gain.

Community

Alternatives comparison must include a documented risk and contingency basis, not only a point-estimate cost. The residents and agencies who inherit the completed work live with that outcome long after the semester ends.

Section D

Learning objectives

By the end of this module you will be able to:

  1. 1.Interpret alternatives analysis framework, using this project's own conditions rather than a textbook case.
  2. 2.Apply weighted decision matrix with documented scoring rationale, using this project's own conditions rather than a textbook case.
  3. 3.Compare value engineering — function analysis and cost-function ratio, using this project's own conditions rather than a textbook case.
  4. 4.Analyze sensitivity of the ranking to criteria weighting, using this project's own conditions rather than a textbook case.
  5. 5.Compute the governing quantity from Value: V = Function / Cost, with a unit audit on every term.
  6. 6.Apply SAVE International Value Methodology Standard (2020), Function analysis and VE job plan, and cite the section that governs your acceptance decision.
  7. 7.Reproduce the worked example for two bridge alternatives and defend the interpretation of the result.
  8. 8.Produce alternatives analysis memo with weighted comparison, value calculation, and documented selection rationale. at a standard the advisor of record would accept without a second revision cycle.

Section E

Instructional content

Full lecture notes with figures and governing equations

Reading design alternatives as a practising engineer

Develops and compares at least two viable design alternatives against the project's governing criteria before selecting a preferred alternative. That single sentence hides the substance of the module: alternatives analysis framework, and weighted decision matrix with documented scoring rationale. Both must be established from project evidence before anything downstream is credible.

In civil engineering practice, this work is the input to the project record. Value engineering — function analysis and cost-function ratio — which is why this page asks you to record the source of every quantity, not just its value. The design of record that drawings, quantities and cost are generated from depends on it.

  • Alternatives analysis framework: technical feasibility, cost, schedule, risk, sustainability
  • Weighted decision matrix with documented scoring rationale
  • Value engineering — function analysis and cost-function ratio
  • Sensitivity of the ranking to criteria weighting
  • Documentation of the rejected alternative's rationale for the record
FIGURE 1Alternative 1Alternative 21Alternative 12Alternative 23Technical score4Cost5Schedule6Risk7Sustainability8Recommendation
Figure 1. Design Alternatives — annotated engineering schematic showing the governing quantities carried through this module.Read this figure alongside the theory block: every labelled quantity must appear in your calculation package with a unit and a source.
Interior of a steel and glass pedestrian bridge showing the structural framing.

Photo 1. Reading design alternatives as a practising engineer in practice — Structural framing of a pedestrian bridge: members, connections and the load path a designer must trace.

Wikimedia Commons, CC BY-SA 4.0

Governing relationships and how they are applied here

The relationships below govern design alternatives. Value: V = Function / Cost — each is valid only inside the parameter range this project occupies, so state that range before substituting.

Weighted decision matrix with documented scoring rationale sets the values you place into these expressions. Any code-prescribed factor must match SAVE International Value Methodology Standard (2020); a factor lifted from a different edition silently changes the answer.

Value: V = Function / Cost

  • Function = performance score (0–1)
  • Cost = life-cycle cost, $
Three engineers in hard hats and safety vests reviewing drawings on a truck tailgate.

Photo 2. Governing relationships and how they are applied here in practice — Field review: the conversation in which a scope, a constraint or a decision is actually settled.

Capstone Studio instructional photograph

Constraints, adopted standards and the safety case for design alternatives

SAVE International Value Methodology Standard (2020), Function analysis and VE job plan, governs this module: Governs value-engineering alternatives comparison ASTM E2782 (2022), Sensitivity analysis guide, adds the second constraint: Governs sensitivity check on alternative-selection weighting

The safety case is explicit here. The failure mode is a decision made without a traceable basis; the people exposed are the owner, the reviewing agency and the engineer of record; the control that prevents it is documentation of the rejected alternative's rationale for the record together with an independent check by someone who did not perform the work.

  • Controlling criterion for this module: alternatives analysis framework.
  • Adopted reference: SAVE International Value Methodology Standard (2020) — cite Function analysis and VE job plan by number.
  • Failure mode guarded: a decision made without a traceable basis.
  • Evidence produced: Alternatives analysis memo with weighted comparison, value calculation, and documented selection rationale..
FIGURE 2Confirm inputs and sourcesSelect governing standardAnalyze / designCheck units and equilibriumIndependent checkAccept or revise
Figure 2. Design Alternatives — professional workflow from inputs through acceptance.The revise loop is normal. Reviewers expect to see it in your version history.
Three engineers in hard hats and safety vests reviewing drawings on a truck tailgate.

Photo 3. Constraints, adopted standards and the safety case for design alternatives in practice — Field review: the conversation in which a scope, a constraint or a decision is actually settled.

Capstone Studio instructional photograph

Where this method stops being valid

The worked example — two bridge alternatives — holds only while its assumptions hold. The precast concrete alternative delivers more function per dollar of life-cycle cost and should be advanced unless a non-cost criterion (e.g., span length limit) governs. Outside that envelope the arithmetic still returns a number, and the number is wrong in a way no unit check will catch.

For this project, the boundary you are most likely to push is documentation of the rejected alternative's rationale for the record. If you cross it, say so in writing, bound the error, and carry the limitation into your results chapter. A disclosed limitation is professional practice; a silent extrapolation is not.

Reinforcing steel and formwork placed in an excavated bridge footing.

Photo 4. Where this method stops being valid in practice — Footing reinforcement and formwork before placement — the physical form of a bearing-capacity calculation.

Wikimedia Commons, public domain

Section F

Engineering workflow

Steps

  1. 1. Assemble the inputs this module needs — alternatives analysis framework; weighted decision matrix with documented scoring rationale — each with a unit and a source record.
  2. 2. Confirm SAVE International Value Methodology Standard (2020) is the adopted edition and locate Function analysis and VE job plan.
  3. 3. State the assumptions and the acceptance criterion for alternatives analysis framework.
  4. 4. Evaluate Value: V = Function / Cost term by term, carrying one extra significant figure.
  5. 5. Test the result against value engineering — function analysis and cost-function ratio.
  6. 6. Audit units and run an order-of-magnitude check by hand before the number leaves your desk.
  7. 7. Obtain an independent check from a teammate who did not perform the work, and record their name and date.
  8. 8. Assemble alternatives analysis memo with weighted comparison, value calculation, and documented selection rationale. and submit it to the advisor of record for review.

Decision points

  • Is every input behind alternatives analysis framework traceable? If not — stop and collect the record.
  • Does the result satisfy weighted decision matrix with documented scoring rationale? If not — revise the work, never the criterion.
  • Would the correction change the design of record that drawings, quantities and cost are generated from? If yes — raise a change-control request before proceeding.
  • Have you ruled out the most common error on this module — presenting only one 'alternative' dressed up as a comparison?

Quality checklist

  • Documented: alternatives analysis framework
  • Documented: weighted decision matrix with documented scoring rationale
  • Documented: value engineering — function analysis and cost-function ratio
  • SAVE International Value Methodology Standard Function analysis and VE job plan cited by section number
  • Units audited on every expression
  • Acceptance criterion recorded before the result
  • Independent check signed and dated
  • Alternatives analysis memo with weighted comparison, value calculation, and documented selection rationale. attached and named per the course convention

Section H

Interactive visualization

Design Alternatives — step-through

Advance one frame at a time. Each frame adds one engineering decision to the previous state.

Stepwise reveal

Step 1 of 6

Define at least two technically feasible alternatives.

Section I

Applicable codes and standards

SAVE International Value Methodology Standard

2020 · Function analysis and VE job plan

Adopted design/analysis reference governing this module.

Relevance: Governs value-engineering alternatives comparison

Reference the section number and edition in your calculation package. Do not reproduce code text.

ASTM E2782

2022 · Sensitivity analysis guide

Adopted design/analysis reference governing this module.

Relevance: Governs sensitivity check on alternative-selection weighting

Reference the section number and edition in your calculation package. Do not reproduce code text.

Section J

Worked examples

Full engineering solution format

Section K

Common mistakes and how to avoid them

  • Presenting only one 'alternative' dressed up as a comparison.
  • Selecting an alternative before the comparison criteria are fixed.
  • Failing to document why the rejected alternative was not selected.
  • Treating alternatives analysis framework as a given instead of establishing it from a project record.
  • Producing alternatives analysis memo with weighted comparison, value calculation, and documented selection rationale. without showing how weighted decision matrix with documented scoring rationale was satisfied.
  • Substituting into Value: V = Function / Cost outside the range where it is valid, and reporting the number anyway.
  • Missing documentation of the rejected alternative's rationale for the record, which is exactly the path to a decision made without a traceable basis.
  • Designing to the average condition when the governing condition is the controlling one.
  • Freezing a design before the constructability and access review that would have changed it.
  • Stopping at output and skipping verification — an unverified number is not an engineering result.
  • Confusing results (what the analysis produced) with conclusions (what the engineer decided).
  • Ignoring constructability: a design that cannot be built safely is not a completed design.

Section L

Industry case study

Big Dig Cost Overrun (Boston, 1991–2007)

Central Artery/Tunnel Project

Official findings

  • Massachusetts Inspector General found the selected alternative's cost estimate ($2.6B) grew to over $14.6B, driven partly by inadequate alternatives-stage risk assessment.

Field observations

  • The controlling assumption was documented nowhere in the design record.
  • No independent check existed at the stage where the error entered the work.

Engineering interpretation

  • Interpretation below is student analysis for instructional purposes, not an official finding.
  • Map the failure to a step in your own workflow and state where your process would have caught it.

Lessons learned

  • Alternatives comparison must include a documented risk and contingency basis, not only a point-estimate cost.

Source: Summarize the published investigation; cite it in your reference list. Do not reproduce copyrighted report text.

Section M

FE Civil exam connection

Handbook FE Reference Handbook — civil engineering practice section (record the section number from your handbook edition).

Exam topics

Engineering economics

Handbook formulas

  • Value = function/cost

Weak results here feed your FE Civil Academy weak-area queue for targeted practice.

Question 1 of 2

Score: 0/2

In design alternatives, which item must be established BEFORE the analysis is run?

Section N

Apply it to your project — Design Alternatives

Complete this using your own capstone project data. Every field is saved to your project record and routed to your advisor with this module's submission.

Inputs and sources

Every value needs a traceable source.

QuantityValueUnitSource / record

Assumptions and consequences

AssumptionBasisConsequence if wrong

Self-check before submission

Section O

Design challenge

Consulting challenge — Design Alternatives

Your firm has been retained to deliver the design alternatives scope for a municipal client on a compressed schedule. Produce the technical position your firm would defend at a public meeting.

Client request: The client wants a defensible recommendation, the basis of design, and an honest statement of what remains unresolved.

Constraints

  • Adopted local code edition governs; no exceptions without written variance.
  • Budget and schedule are fixed; scope changes require change control.
  • Public safety and accessibility requirements are non-negotiable.

Deliverables

  • One-page basis of design
  • Supporting calculation extract
  • Risk and limitation statement

Evaluation

  • Technical correctness
  • Standard compliance
  • Clarity of engineering judgment
  • Honest treatment of uncertainty

Section P

Documentation workspace

Write the report section for this module in the academic editor

Loading editor…
0 words

Section Q

File uploads

Accepted: PDF, DOCX, XLSX, CSV, PNG, JPG, ZIP

No files uploaded yet.

Section R

Deliverable and advisor review

Alternatives analysis memo with weighted comparison, value calculation, and documented selection rationale.

Engineering design
Technical analysis
Code compliance
Calculation quality
Drawings

Submissions route to your assigned faculty advisor and are scored independently by faculty and administrator rubrics.

Reflection

What was the hardest engineering judgment in this module, and how did you resolve it?

Section S

ABET outcome mapping

SO 2
CE-PC4
reinforced

Alternatives analysis memo with weighted comparison, value calculation, and documented selection rationale. with advisor review and dual scoring.

Assessment: Faculty rubric score and administrator rubric score on this module's submission.

Rubric: Engineering design · Target: 70% of students at or above 'meets expectations'.

Section T

References and further study

standard

SAVE International Value Methodology Standard (2020)

Adopted reference — cite section numbers, do not reproduce text.

standard

ASTM E2782 (2022)

Adopted reference — cite section numbers, do not reproduce text.

template

Design Alternatives — instructor design procedure

Course template for the calculation package format expected in the final report appendix.

manual

NCEES FE Reference Handbook

Locate the equations used here and note the handbook section for exam recall.

template

Advisor meeting agenda item

Bring the unresolved decision from this module to your next weekly advisor meeting.

Week 5 · Alternatives analysis memo with weighted comparison, value calculation, and documented selection rationale.
© 2026 Dr. Steve Efe. Civil Engineering Capstone Studio. All rights reserved.