Benefit-Cost Analysis
Engineering Economics · FE Reference Handbook section
Handbook notes for this section
Definitions and conditions exactly as the handbook states them.
- In a benefit-cost analysis, the benefits B of a project should exceed the estimated costs C.
- Modified Accelerated Cost Recovery System (MACRS)
- The following symbols are used to model decisions with decision trees:
- Decision node D2 Decision maker chooses 1 of the available paths.
- Chance node C2 Represents a probabilistic (chance) event. Each possible outcome (C1, C2,..., CY)
- Outcome node Shows result for a particular path through the decision tree.
Core formulas for this FE topic
Definitions, applicability, units, assumptions and worked examples for each relation.
Worked exam-style examples
The four ways this section is written on the real exam — thoughts first, then equations, then substitution.
A culvert costs $85,000 now and $4,000 per year to maintain for 20 years. At i = 6%, what is the present worth of the total cost?
Given
P₀ = $85,000
A = $4,000/yr
Find
Total present worth
Start with the thinking
- Uniform series converts with (P/A, i, n).
- Costs are all negative — keep one sign convention.
Step-by-step solution
Series factor
Growth term
Factor
Maintenance PW — 4,000(11.47) = $45,880
Total — PW = 85,000 + 45,880 = $130,880
PW ≈ $131,000
Why the other options are there
- $165,000 (annual costs summed undiscounted)
- $45,900 (initial cost omitted)
Reference: FE Reference Handbook — Engineering Economics — Uniform series
A widening saves $210,000 per year in delay, costs $1.6 M to build (20-yr life, i = 7%, no salvage) and $30,000 per year to maintain. Compute B/C.
Given
Benefits = $210,000/yr
First cost = $1,600,000
O&M = $30,000/yr
Find
Benefit-cost ratio
Start with the thinking
- Convert everything to the same time basis — annual is easiest here.
- Maintenance belongs in the denominator, not as a negative benefit.
Step-by-step solution
Capital recovery
Growth term
Factor
Annual cost — 1,600,000(0.09439) + 30,000 = 151,024 + 30,000 = $181,024
Ratio
Why the other options are there
- 1.31 (O&M left out)
- 0.86 (ratio inverted)
Reference: FE Reference Handbook — Engineering Economics — Benefit-cost analysis
A public improvement costs $784,000 with $17,000 annual maintenance and yields $84,000 of annual benefits over 35 years at 4.5%. What is B/C?
Given
C = $784,000
M = $17,000/yr
B = $84,000/yr
Find
B/C ratio
Start with the thinking
- Convert the first cost to an equivalent uniform annual cost.
- Maintenance belongs in the denominator, not netted from benefits.
Step-by-step solution
Capital recovery
Evaluate
Annual cost of capital — EUAC = $784,000 × 0.05727 = $44,900/yr
Ratio — B/C = $84,000/($44,900 + $17,000) = 1.357
Decision — B/C ≥ 1, project justified
B/C ≈ 1.36 → justified
Why the other options are there
- 4.94 (capital cost omitted)
- 0.107 (first cost not annualised)
Reference: FE Reference Handbook — Engineering Economics → Benefit-Cost Analysis
A public improvement costs $569,000 with $18,000 annual maintenance and yields $148,000 of annual benefits over 22 years at 5.0%. What is B/C?
Given
C = $569,000
M = $18,000/yr
B = $148,000/yr
Find
B/C ratio
Start with the thinking
- Convert the first cost to an equivalent uniform annual cost.
- Maintenance belongs in the denominator, not netted from benefits.
Step-by-step solution
Capital recovery
Evaluate
Annual cost of capital — EUAC = $569,000 × 0.07597 = $43,227/yr
Ratio — B/C = $148,000/($43,227 + $18,000) = 2.417
Decision — B/C ≥ 1, project justified
B/C ≈ 2.42 → justified
Why the other options are there
- 8.22 (capital cost omitted)
- 0.260 (first cost not annualised)
Reference: FE Reference Handbook — Engineering Economics → Benefit-Cost Analysis
A public improvement costs $1,164,000 with $24,000 annual maintenance and yields $123,000 of annual benefits over 22 years at 5.0%. What is B/C?
Given
C = $1,164,000
M = $24,000/yr
B = $123,000/yr
Find
B/C ratio
Start with the thinking
- Convert the first cost to an equivalent uniform annual cost.
- Maintenance belongs in the denominator, not netted from benefits.
Step-by-step solution
Capital recovery
Evaluate
Annual cost of capital — EUAC = $1,164,000 × 0.07597 = $88,430/yr
Ratio — B/C = $123,000/($88,430 + $24,000) = 1.094
Decision — B/C ≥ 1, project justified
B/C ≈ 1.09 → justified
Why the other options are there
- 5.13 (capital cost omitted)
- 0.106 (first cost not annualised)
Reference: FE Reference Handbook — Engineering Economics → Benefit-Cost Analysis
A public improvement costs $693,000 with $36,000 annual maintenance and yields $133,000 of annual benefits over 38 years at 4.0%. What is B/C?
Given
C = $693,000
M = $36,000/yr
B = $133,000/yr
Find
B/C ratio
Start with the thinking
- Convert the first cost to an equivalent uniform annual cost.
- Maintenance belongs in the denominator, not netted from benefits.
Step-by-step solution
Capital recovery
Evaluate
Annual cost of capital — EUAC = $693,000 × 0.05163 = $35,781/yr
Ratio — B/C = $133,000/($35,781 + $36,000) = 1.853
Decision — B/C ≥ 1, project justified
B/C ≈ 1.85 → justified
Why the other options are there
- 3.69 (capital cost omitted)
- 0.192 (first cost not annualised)
Reference: FE Reference Handbook — Engineering Economics → Benefit-Cost Analysis
A public improvement costs $999,000 with $28,000 annual maintenance and yields $137,000 of annual benefits over 36 years at 6.0%. What is B/C?
Given
C = $999,000
M = $28,000/yr
B = $137,000/yr
Find
B/C ratio
Start with the thinking
- Convert the first cost to an equivalent uniform annual cost.
- Maintenance belongs in the denominator, not netted from benefits.
Step-by-step solution
Capital recovery
Evaluate
Annual cost of capital — EUAC = $999,000 × 0.06839 = $68,326/yr
Ratio — B/C = $137,000/($68,326 + $28,000) = 1.422
Decision — B/C ≥ 1, project justified
B/C ≈ 1.42 → justified
Why the other options are there
- 4.89 (capital cost omitted)
- 0.137 (first cost not annualised)
Reference: FE Reference Handbook — Engineering Economics → Benefit-Cost Analysis
A public improvement costs $1,149,000 with $30,000 annual maintenance and yields $180,000 of annual benefits over 31 years at 7.5%. What is B/C?
Given
C = $1,149,000
M = $30,000/yr
B = $180,000/yr
Find
B/C ratio
Start with the thinking
- Convert the first cost to an equivalent uniform annual cost.
- Maintenance belongs in the denominator, not netted from benefits.
Step-by-step solution
Capital recovery
Evaluate
Annual cost of capital — EUAC = $1,149,000 × 0.08392 = $96,420/yr
Ratio — B/C = $180,000/($96,420 + $30,000) = 1.424
Decision — B/C ≥ 1, project justified
B/C ≈ 1.42 → justified
Why the other options are there
- 6.00 (capital cost omitted)
- 0.157 (first cost not annualised)
Reference: FE Reference Handbook — Engineering Economics → Benefit-Cost Analysis
A public improvement costs $605,000 with $34,000 annual maintenance and yields $73,000 of annual benefits over 34 years at 4.5%. What is B/C?
Given
C = $605,000
M = $34,000/yr
B = $73,000/yr
Find
B/C ratio
Start with the thinking
- Convert the first cost to an equivalent uniform annual cost.
- Maintenance belongs in the denominator, not netted from benefits.
Step-by-step solution
Capital recovery
Evaluate
Annual cost of capital — EUAC = $605,000 × 0.05798 = $35,079/yr
Ratio — B/C = $73,000/($35,079 + $34,000) = 1.057
Decision — B/C ≥ 1, project justified
B/C ≈ 1.06 → justified
Why the other options are there
- 2.15 (capital cost omitted)
- 0.121 (first cost not annualised)
Reference: FE Reference Handbook — Engineering Economics → Benefit-Cost Analysis
A public improvement costs $872,000 with $17,000 annual maintenance and yields $120,000 of annual benefits over 27 years at 5.0%. What is B/C?
Given
C = $872,000
M = $17,000/yr
B = $120,000/yr
Find
B/C ratio
Start with the thinking
- Convert the first cost to an equivalent uniform annual cost.
- Maintenance belongs in the denominator, not netted from benefits.
Step-by-step solution
Capital recovery
Evaluate
Annual cost of capital — EUAC = $872,000 × 0.06829 = $59,551/yr
Ratio — B/C = $120,000/($59,551 + $17,000) = 1.568
Decision — B/C ≥ 1, project justified
B/C ≈ 1.57 → justified
Why the other options are there
- 7.06 (capital cost omitted)
- 0.138 (first cost not annualised)
Reference: FE Reference Handbook — Engineering Economics → Benefit-Cost Analysis