Forecasting
Construction Engineering · FE Reference Handbook section
Core formulas for this FE topic
Definitions, applicability, units, assumptions and worked examples for each relation.
Worked exam-style examples
The four ways this section is written on the real exam — thoughts first, then equations, then substitution.
A construction engineering problem uses Total cost from unit cost. Given unit cost (cu) = 243.5 $/unit; quantity (Q) = 7,204 units, determine the total cost (C) in $.
Given
unit cost (cu) = 243.5 $/unit
Find
total cost (C), in $
Start with the thinking
- The governing relation printed in this handbook section is Total cost from unit cost.
- Everything except C is given, so isolate C symbolically first — never rearrange after the numbers are in.
- Tabulate each given with its unit and confirm the units are consistent with the relation before substituting.
- Construction Engineering items reward recognising the unknown before touching a calculator.
Step-by-step solution
Step 1 — State the governing relation:
Step 2 — Rearrange the relation so that C stands alone on the left-hand side.
Step 3 — List the givens: unit cost (cu) = 243.5 $/unit, quantity (Q) = 7,204 units.
Step 4 — Substitute the given values into the rearranged relation.
Step 5 — Evaluate:
Step 6 — Check: returning C = 1,754,174 $ to
reproduces the given quantities, and both sides carry the same units.
Why the other options are there
- 3,508,348 — kept a factor of two that cancels in the correct rearrangement.
- 877,087 — dropped that same factor in the other direction.
- 1,929,591 — rounded an intermediate value before the final step.
Reference: FE Reference Handbook — Construction Engineering → Forecasting
A construction engineering problem uses Total cost from unit cost. Given quantity (Q) = 6,681 units; total cost (C) = 229,395 $, determine the unit cost (cu) in $/unit.
Given
total cost (C) = 229,395 $
Find
unit cost (cu), in $/unit
Start with the thinking
- The governing relation printed in this handbook section is Total cost from unit cost.
- Everything except cu is given, so isolate cu symbolically first — never rearrange after the numbers are in.
- Tabulate each given with its unit and confirm the units are consistent with the relation before substituting.
- Construction Engineering items reward recognising the unknown before touching a calculator.
Step-by-step solution
Step 1 — State the governing relation:
Step 2 — Rearrange the relation so that cu stands alone on the left-hand side.
Step 3 — List the givens: quantity (Q) = 6,681 units, total cost (C) = 229,395 $.
Step 4 — Substitute the given values into the rearranged relation.
Step 5 — Evaluate:
Step 6 — Check: returning cu = 34.3354 $/unit to
reproduces the given quantities, and both sides carry the same units.
Why the other options are there
- 68.6709 — kept a factor of two that cancels in the correct rearrangement.
- 17.1677 — dropped that same factor in the other direction.
- 37.7690 — rounded an intermediate value before the final step.
Reference: FE Reference Handbook — Construction Engineering → Forecasting
A construction engineering problem uses Total cost from unit cost. Given unit cost (cu) = 236.5 $/unit; total cost (C) = 335,181 $, determine the quantity (Q) in units.
Given
unit cost (cu) = 236.5 $/unit
total cost (C) = 335,181 $
Find
quantity (Q), in units
Start with the thinking
- The governing relation printed in this handbook section is Total cost from unit cost.
- Everything except Q is given, so isolate Q symbolically first — never rearrange after the numbers are in.
- Tabulate each given with its unit and confirm the units are consistent with the relation before substituting.
- Construction Engineering items reward recognising the unknown before touching a calculator.
Step-by-step solution
Step 1 — State the governing relation:
Step 2 — Rearrange the relation so that Q stands alone on the left-hand side.
Step 3 — List the givens: unit cost (cu) = 236.5 $/unit, total cost (C) = 335,181 $.
Step 4 — Substitute the given values into the rearranged relation.
Step 5 — Evaluate:
Step 6 — Check: returning Q = 1,417 units to
reproduces the given quantities, and both sides carry the same units.
Why the other options are there
- 2,835 — kept a factor of two that cancels in the correct rearrangement.
- 708.6 — dropped that same factor in the other direction.
- 1,559 — rounded an intermediate value before the final step.
Reference: FE Reference Handbook — Construction Engineering → Forecasting
A construction engineering problem uses Total cost from unit cost. Given unit cost (cu) = 146.5 $/unit; quantity (Q) = 3,225 units, determine the total cost (C) in $.
Given
unit cost (cu) = 146.5 $/unit
Find
total cost (C), in $
Start with the thinking
- The governing relation printed in this handbook section is Total cost from unit cost.
- Everything except C is given, so isolate C symbolically first — never rearrange after the numbers are in.
- Tabulate each given with its unit and confirm the units are consistent with the relation before substituting.
- Construction Engineering items reward recognising the unknown before touching a calculator.
Step-by-step solution
Step 1 — State the governing relation:
Step 2 — Rearrange the relation so that C stands alone on the left-hand side.
Step 3 — List the givens: unit cost (cu) = 146.5 $/unit, quantity (Q) = 3,225 units.
Step 4 — Substitute the given values into the rearranged relation.
Step 5 — Evaluate:
Step 6 — Check: returning C = 472,463 $ to
reproduces the given quantities, and both sides carry the same units.
Why the other options are there
- 944,925 — kept a factor of two that cancels in the correct rearrangement.
- 236,231 — dropped that same factor in the other direction.
- 519,709 — rounded an intermediate value before the final step.
Reference: FE Reference Handbook — Construction Engineering → Forecasting
A construction engineering problem uses Total cost from unit cost. Given quantity (Q) = 2,953 units; total cost (C) = 76,133 $, determine the unit cost (cu) in $/unit.
Given
total cost (C) = 76,133 $
Find
unit cost (cu), in $/unit
Start with the thinking
- The governing relation printed in this handbook section is Total cost from unit cost.
- Everything except cu is given, so isolate cu symbolically first — never rearrange after the numbers are in.
- Tabulate each given with its unit and confirm the units are consistent with the relation before substituting.
- Construction Engineering items reward recognising the unknown before touching a calculator.
Step-by-step solution
Step 1 — State the governing relation:
Step 2 — Rearrange the relation so that cu stands alone on the left-hand side.
Step 3 — List the givens: quantity (Q) = 2,953 units, total cost (C) = 76,133 $.
Step 4 — Substitute the given values into the rearranged relation.
Step 5 — Evaluate:
Step 6 — Check: returning cu = 25.7816 $/unit to
reproduces the given quantities, and both sides carry the same units.
Why the other options are there
- 51.5632 — kept a factor of two that cancels in the correct rearrangement.
- 12.8908 — dropped that same factor in the other direction.
- 28.3597 — rounded an intermediate value before the final step.
Reference: FE Reference Handbook — Construction Engineering → Forecasting
A construction engineering problem uses Total cost from unit cost. Given unit cost (cu) = 249.5 $/unit; total cost (C) = 21,553 $, determine the quantity (Q) in units.
Given
unit cost (cu) = 249.5 $/unit
total cost (C) = 21,553 $
Find
quantity (Q), in units
Start with the thinking
- The governing relation printed in this handbook section is Total cost from unit cost.
- Everything except Q is given, so isolate Q symbolically first — never rearrange after the numbers are in.
- Tabulate each given with its unit and confirm the units are consistent with the relation before substituting.
- Construction Engineering items reward recognising the unknown before touching a calculator.
Step-by-step solution
Step 1 — State the governing relation:
Step 2 — Rearrange the relation so that Q stands alone on the left-hand side.
Step 3 — List the givens: unit cost (cu) = 249.5 $/unit, total cost (C) = 21,553 $.
Step 4 — Substitute the given values into the rearranged relation.
Step 5 — Evaluate:
Step 6 — Check: returning Q = 86.3848 units to
reproduces the given quantities, and both sides carry the same units.
Why the other options are there
- 172.8 — kept a factor of two that cancels in the correct rearrangement.
- 43.1924 — dropped that same factor in the other direction.
- 95.0232 — rounded an intermediate value before the final step.
Reference: FE Reference Handbook — Construction Engineering → Forecasting
A construction engineering problem uses Total cost from unit cost. Given unit cost (cu) = 10.5000 $/unit; quantity (Q) = 3,831 units, determine the total cost (C) in $.
Given
unit cost (cu) = 10.5000 $/unit
Find
total cost (C), in $
Start with the thinking
- The governing relation printed in this handbook section is Total cost from unit cost.
- Everything except C is given, so isolate C symbolically first — never rearrange after the numbers are in.
- Tabulate each given with its unit and confirm the units are consistent with the relation before substituting.
- Construction Engineering items reward recognising the unknown before touching a calculator.
Step-by-step solution
Step 1 — State the governing relation:
Step 2 — Rearrange the relation so that C stands alone on the left-hand side.
Step 3 — List the givens: unit cost (cu) = 10.5000 $/unit, quantity (Q) = 3,831 units.
Step 4 — Substitute the given values into the rearranged relation.
Step 5 — Evaluate:
Step 6 — Check: returning C = 40,226 $ to
reproduces the given quantities, and both sides carry the same units.
Why the other options are there
- 80,451 — kept a factor of two that cancels in the correct rearrangement.
- 20,113 — dropped that same factor in the other direction.
- 44,248 — rounded an intermediate value before the final step.
Reference: FE Reference Handbook — Construction Engineering → Forecasting
A construction engineering problem uses Total cost from unit cost. Given quantity (Q) = 1,683 units; total cost (C) = 36,441 $, determine the unit cost (cu) in $/unit.
Given
total cost (C) = 36,441 $
Find
unit cost (cu), in $/unit
Start with the thinking
- The governing relation printed in this handbook section is Total cost from unit cost.
- Everything except cu is given, so isolate cu symbolically first — never rearrange after the numbers are in.
- Tabulate each given with its unit and confirm the units are consistent with the relation before substituting.
- Construction Engineering items reward recognising the unknown before touching a calculator.
Step-by-step solution
Step 1 — State the governing relation:
Step 2 — Rearrange the relation so that cu stands alone on the left-hand side.
Step 3 — List the givens: quantity (Q) = 1,683 units, total cost (C) = 36,441 $.
Step 4 — Substitute the given values into the rearranged relation.
Step 5 — Evaluate:
Step 6 — Check: returning cu = 21.6524 $/unit to
reproduces the given quantities, and both sides carry the same units.
Why the other options are there
- 43.3048 — kept a factor of two that cancels in the correct rearrangement.
- 10.8262 — dropped that same factor in the other direction.
- 23.8176 — rounded an intermediate value before the final step.
Reference: FE Reference Handbook — Construction Engineering → Forecasting
A construction engineering problem uses Total cost from unit cost. Given unit cost (cu) = 400.0 $/unit; total cost (C) = 435,908 $, determine the quantity (Q) in units.
Given
unit cost (cu) = 400.0 $/unit
total cost (C) = 435,908 $
Find
quantity (Q), in units
Start with the thinking
- The governing relation printed in this handbook section is Total cost from unit cost.
- Everything except Q is given, so isolate Q symbolically first — never rearrange after the numbers are in.
- Tabulate each given with its unit and confirm the units are consistent with the relation before substituting.
- Construction Engineering items reward recognising the unknown before touching a calculator.
Step-by-step solution
Step 1 — State the governing relation:
Step 2 — Rearrange the relation so that Q stands alone on the left-hand side.
Step 3 — List the givens: unit cost (cu) = 400.0 $/unit, total cost (C) = 435,908 $.
Step 4 — Substitute the given values into the rearranged relation.
Step 5 — Evaluate:
Step 6 — Check: returning Q = 1,090 units to
reproduces the given quantities, and both sides carry the same units.
Why the other options are there
- 2,180 — kept a factor of two that cancels in the correct rearrangement.
- 544.9 — dropped that same factor in the other direction.
- 1,199 — rounded an intermediate value before the final step.
Reference: FE Reference Handbook — Construction Engineering → Forecasting
A construction engineering problem uses Total cost from unit cost. Given unit cost (cu) = 87.5000 $/unit; quantity (Q) = 2,132 units, determine the total cost (C) in $.
Given
unit cost (cu) = 87.5000 $/unit
Find
total cost (C), in $
Start with the thinking
- The governing relation printed in this handbook section is Total cost from unit cost.
- Everything except C is given, so isolate C symbolically first — never rearrange after the numbers are in.
- Tabulate each given with its unit and confirm the units are consistent with the relation before substituting.
- Construction Engineering items reward recognising the unknown before touching a calculator.
Step-by-step solution
Step 1 — State the governing relation:
Step 2 — Rearrange the relation so that C stands alone on the left-hand side.
Step 3 — List the givens: unit cost (cu) = 87.5000 $/unit, quantity (Q) = 2,132 units.
Step 4 — Substitute the given values into the rearranged relation.
Step 5 — Evaluate:
Step 6 — Check: returning C = 186,550 $ to
reproduces the given quantities, and both sides carry the same units.
Why the other options are there
- 373,100 — kept a factor of two that cancels in the correct rearrangement.
- 93,275 — dropped that same factor in the other direction.
- 205,205 — rounded an intermediate value before the final step.
Reference: FE Reference Handbook — Construction Engineering → Forecasting