Construction
Construction Engineering · FE Reference Handbook section
Handbook notes for this section
Definitions and conditions exactly as the handbook states them.
- Construction project scheduling and analysis questions may be based on either the activity-on-node method or the activity-on-
- DEPENDS ON THE START OF A DEPENDS ON THE FINISH OF A DEPENDS ON THE FINISH OF A
- ACTIVITY-ON-ARROW ANNOTATION ACTIVITY-ON-NODE ANNOTATION
- EARLY START/LATE START EARLY FINISH/LATE FINISH EARLY EARLY
Core formulas for this FE topic
Definitions, applicability, units, assumptions and worked examples for each relation.
This section is conceptual; there are no equations to memorise.
Worked exam-style examples
The four ways this section is written on the real exam — thoughts first, then equations, then substitution.
A $6.0M project reports planned value $3,900,000, earned value $4,320,000 and actual cost $5,356,800 at the reporting date. Compute the cost and schedule variances, both performance indices, and forecast the estimate at completion.
Given
BAC = $6,000,000
PV = $3,900,000
EV = $4,320,000
AC = $5,356,800
Find
CV, SV, CPI, SPI and EAC
Start with the thinking
- Earned-value analysis compares what was accomplished (EV) with what was spent (AC) and what was scheduled (PV).
- An index below 1.00 signals an overrun; the forecast divides the budget by the cost index.
Step-by-step solution
Formula
Substituting — CV = 4,320,000 − 5,356,800 = $-1,036,800
Formula
Substituting — SV = 4,320,000 − 3,900,000 = $420,000
Indices
Formula
Substituting — EAC = 6,000,000/0.806 = $7,440,000
CPI = 0.81, SPI = 1.11, EAC ≈ $7,440,000
Why the other options are there
- EAC = $4,838,710 (multiplied by the index)
- CPI = 1.240 (inverted)
Reference: FE Reference Handbook — Construction Engineering → Construction
A $6.0M project reports planned value $2,100,000, earned value $1,980,000 and actual cost $1,920,600 at the reporting date. Compute the cost and schedule variances, both performance indices, and forecast the estimate at completion.
Given
BAC = $6,000,000
PV = $2,100,000
EV = $1,980,000
AC = $1,920,600
Find
CV, SV, CPI, SPI and EAC
Start with the thinking
- Earned-value analysis compares what was accomplished (EV) with what was spent (AC) and what was scheduled (PV).
- An index below 1.00 signals an overrun; the forecast divides the budget by the cost index.
Step-by-step solution
Formula
Substituting — CV = 1,980,000 − 1,920,600 = $59,400
Formula
Substituting — SV = 1,980,000 − 2,100,000 = $-120,000
Indices
Formula
Substituting — EAC = 6,000,000/1.031 = $5,820,000
CPI = 1.03, SPI = 0.94, EAC ≈ $5,820,000
Why the other options are there
- EAC = $6,185,567 (multiplied by the index)
- CPI = 0.970 (inverted)
Reference: FE Reference Handbook — Construction Engineering → Construction
A $5.0M project reports planned value $1,500,000, earned value $1,650,000 and actual cost $1,815,000 at the reporting date. Compute the cost and schedule variances, both performance indices, and forecast the estimate at completion.
Given
BAC = $5,000,000
PV = $1,500,000
EV = $1,650,000
AC = $1,815,000
Find
CV, SV, CPI, SPI and EAC
Start with the thinking
- Earned-value analysis compares what was accomplished (EV) with what was spent (AC) and what was scheduled (PV).
- An index below 1.00 signals an overrun; the forecast divides the budget by the cost index.
Step-by-step solution
Formula
Substituting — CV = 1,650,000 − 1,815,000 = $-165,000
Formula
Substituting — SV = 1,650,000 − 1,500,000 = $150,000
Indices
Formula
Substituting — EAC = 5,000,000/0.909 = $5,500,000
CPI = 0.91, SPI = 1.10, EAC ≈ $5,500,000
Why the other options are there
- EAC = $4,545,455 (multiplied by the index)
- CPI = 1.100 (inverted)
Reference: FE Reference Handbook — Construction Engineering → Construction
A $12.0M project reports planned value $4,200,000, earned value $4,440,000 and actual cost $4,884,000 at the reporting date. Compute the cost and schedule variances, both performance indices, and forecast the estimate at completion.
Given
BAC = $12,000,000
PV = $4,200,000
EV = $4,440,000
AC = $4,884,000
Find
CV, SV, CPI, SPI and EAC
Start with the thinking
- Earned-value analysis compares what was accomplished (EV) with what was spent (AC) and what was scheduled (PV).
- An index below 1.00 signals an overrun; the forecast divides the budget by the cost index.
Step-by-step solution
Formula
Substituting — CV = 4,440,000 − 4,884,000 = $-444,000
Formula
Substituting — SV = 4,440,000 − 4,200,000 = $240,000
Indices
Formula
Substituting — EAC = 12,000,000/0.909 = $13,200,000
CPI = 0.91, SPI = 1.06, EAC ≈ $13,200,000
Why the other options are there
- EAC = $10,909,091 (multiplied by the index)
- CPI = 1.100 (inverted)
Reference: FE Reference Handbook — Construction Engineering → Construction
A $4.0M project reports planned value $2,400,000, earned value $2,280,000 and actual cost $2,143,200 at the reporting date. Compute the cost and schedule variances, both performance indices, and forecast the estimate at completion.
Given
BAC = $4,000,000
PV = $2,400,000
EV = $2,280,000
AC = $2,143,200
Find
CV, SV, CPI, SPI and EAC
Start with the thinking
- Earned-value analysis compares what was accomplished (EV) with what was spent (AC) and what was scheduled (PV).
- An index below 1.00 signals an overrun; the forecast divides the budget by the cost index.
Step-by-step solution
Formula
Substituting — CV = 2,280,000 − 2,143,200 = $136,800
Formula
Substituting — SV = 2,280,000 − 2,400,000 = $-120,000
Indices
Formula
Substituting — EAC = 4,000,000/1.064 = $3,760,000
CPI = 1.06, SPI = 0.95, EAC ≈ $3,760,000
Why the other options are there
- EAC = $4,255,319 (multiplied by the index)
- CPI = 0.940 (inverted)
Reference: FE Reference Handbook — Construction Engineering → Construction
A $4.0M project reports planned value $1,800,000, earned value $1,320,000 and actual cost $1,372,800 at the reporting date. Compute the cost and schedule variances, both performance indices, and forecast the estimate at completion.
Given
BAC = $4,000,000
PV = $1,800,000
EV = $1,320,000
AC = $1,372,800
Find
CV, SV, CPI, SPI and EAC
Start with the thinking
- Earned-value analysis compares what was accomplished (EV) with what was spent (AC) and what was scheduled (PV).
- An index below 1.00 signals an overrun; the forecast divides the budget by the cost index.
Step-by-step solution
Formula
Substituting — CV = 1,320,000 − 1,372,800 = $-52,800
Formula
Substituting — SV = 1,320,000 − 1,800,000 = $-480,000
Indices
Formula
Substituting — EAC = 4,000,000/0.962 = $4,160,000
CPI = 0.96, SPI = 0.73, EAC ≈ $4,160,000
Why the other options are there
- EAC = $3,846,154 (multiplied by the index)
- CPI = 1.040 (inverted)
Reference: FE Reference Handbook — Construction Engineering → Construction
A $8.0M project reports planned value $4,400,000, earned value $3,600,000 and actual cost $3,276,000 at the reporting date. Compute the cost and schedule variances, both performance indices, and forecast the estimate at completion.
Given
BAC = $8,000,000
PV = $4,400,000
EV = $3,600,000
AC = $3,276,000
Find
CV, SV, CPI, SPI and EAC
Start with the thinking
- Earned-value analysis compares what was accomplished (EV) with what was spent (AC) and what was scheduled (PV).
- An index below 1.00 signals an overrun; the forecast divides the budget by the cost index.
Step-by-step solution
Formula
Substituting — CV = 3,600,000 − 3,276,000 = $324,000
Formula
Substituting — SV = 3,600,000 − 4,400,000 = $-800,000
Indices
Formula
Substituting — EAC = 8,000,000/1.099 = $7,280,000
CPI = 1.10, SPI = 0.82, EAC ≈ $7,280,000
Why the other options are there
- EAC = $8,791,209 (multiplied by the index)
- CPI = 0.910 (inverted)
Reference: FE Reference Handbook — Construction Engineering → Construction
A $12.0M project reports planned value $5,400,000, earned value $6,240,000 and actual cost $7,488,000 at the reporting date. Compute the cost and schedule variances, both performance indices, and forecast the estimate at completion.
Given
BAC = $12,000,000
PV = $5,400,000
EV = $6,240,000
AC = $7,488,000
Find
CV, SV, CPI, SPI and EAC
Start with the thinking
- Earned-value analysis compares what was accomplished (EV) with what was spent (AC) and what was scheduled (PV).
- An index below 1.00 signals an overrun; the forecast divides the budget by the cost index.
Step-by-step solution
Formula
Substituting — CV = 6,240,000 − 7,488,000 = $-1,248,000
Formula
Substituting — SV = 6,240,000 − 5,400,000 = $840,000
Indices
Formula
Substituting — EAC = 12,000,000/0.833 = $14,400,000
CPI = 0.83, SPI = 1.16, EAC ≈ $14,400,000
Why the other options are there
- EAC = $10,000,000 (multiplied by the index)
- CPI = 1.200 (inverted)
Reference: FE Reference Handbook — Construction Engineering → Construction
A $10.0M project reports planned value $3,500,000, earned value $2,300,000 and actual cost $2,208,000 at the reporting date. Compute the cost and schedule variances, both performance indices, and forecast the estimate at completion.
Given
BAC = $10,000,000
PV = $3,500,000
EV = $2,300,000
AC = $2,208,000
Find
CV, SV, CPI, SPI and EAC
Start with the thinking
- Earned-value analysis compares what was accomplished (EV) with what was spent (AC) and what was scheduled (PV).
- An index below 1.00 signals an overrun; the forecast divides the budget by the cost index.
Step-by-step solution
Formula
Substituting — CV = 2,300,000 − 2,208,000 = $92,000
Formula
Substituting — SV = 2,300,000 − 3,500,000 = $-1,200,000
Indices
Formula
Substituting — EAC = 10,000,000/1.042 = $9,600,000
CPI = 1.04, SPI = 0.66, EAC ≈ $9,600,000
Why the other options are there
- EAC = $10,416,667 (multiplied by the index)
- CPI = 0.960 (inverted)
Reference: FE Reference Handbook — Construction Engineering → Construction
A $8.0M project reports planned value $4,400,000, earned value $3,600,000 and actual cost $4,392,000 at the reporting date. Compute the cost and schedule variances, both performance indices, and forecast the estimate at completion.
Given
BAC = $8,000,000
PV = $4,400,000
EV = $3,600,000
AC = $4,392,000
Find
CV, SV, CPI, SPI and EAC
Start with the thinking
- Earned-value analysis compares what was accomplished (EV) with what was spent (AC) and what was scheduled (PV).
- An index below 1.00 signals an overrun; the forecast divides the budget by the cost index.
Step-by-step solution
Formula
Substituting — CV = 3,600,000 − 4,392,000 = $-792,000
Formula
Substituting — SV = 3,600,000 − 4,400,000 = $-800,000
Indices
Formula
Substituting — EAC = 8,000,000/0.820 = $9,760,000
CPI = 0.82, SPI = 0.82, EAC ≈ $9,760,000
Why the other options are there
- EAC = $6,557,377 (multiplied by the index)
- CPI = 1.220 (inverted)
Reference: FE Reference Handbook — Construction Engineering → Construction