CEGR 492 · Engineering Design Studio · Water Resources Engineering

Drainage and Stormwater

Inlet capture during rainfall: gutter spread and inlet capacity decide whether the lane floods.

Phase VI · Engineering Design Studio · Week 5–8

Drainage and Stormwater Design Studio

Design inlets, storm sewers, swales and detention/retention systems to meet release-rate requirements.

HEC-22
Local stormwater manual
Module progress0%

Drainage elements designed

0

Checks passing

0

0 checks recorded

Open warnings

0

No drainage element yet

Add a drainage element to record its inputs, capacity and governing check.

Learning objectives

  • Size storm sewer pipes
  • Design inlets and swales
  • Size detention volume

Engineering judgment

  • Design for the conveyance storm and check the extreme storm.
  • Tailwater controls outlet design.

Governing standards

  • NRCS TR-55

    Urban Hydrology for Small Watersheds

    Runoff curve numbers, time of concentration, peak flow

    Ch. 2 CN
    Ch. 3 Tc
    Ch. 4 Peak
  • FHWA HEC-22

    Urban Drainage Design Manual

    Inlets, storm sewers, detention

    Ch. 4 Inlets
    Ch. 7 Storm drains

FE Civil connection

Storm drainage

Handbook section: Water Resources

Practice this FE topic

Recommended next step

Culvert, Weir, and Open-Channel Studio

Design culverts, weirs, channels and energy dissipators with inlet/outlet control and scour protection.

Continue
© 2026 Civil Engineering Capstone Studio. All rights reserved.